Update construction progress of Tamada Office and Warehouse project in September 2019

In September 2019, at the Tamada Office and Warehouse project, INVESTCORP Myanmar has completed 100% of the finishing work of the main workshop and is carrying out cleaning.

At the office area, the whole construction work has also been completed and is being cleaned.

At the outdoor area, the construction of fences, yard, concrete roads and drainage system have been 100% completed. The leveling of grass area around the house has also been completed to 95%. Currently, some of the remaining finishing works, such as painting the fence and gate, are being urgently completed by INVESTCORP Myanmar to keep up with the handingover progress of the project in October 2019.