Update construction progress of Textile dyeing and garment factory project– Ramatex Nam Dinh in August 2019

By the end of August 2019, at the dyeing area, INVESTCORP has completed the entire construction and handed over to the Owner.

At the textile area, INVESTCORP has finished construction of false ceiling items, installation of shutter doors, doors and windows. Painting and tiling works of the toilets and auxiliary rooms were basically completed. The remaining works such as roofing and outdoor painting are expected to be completed in September 2019.

At the office area, INVESTCORP has completed construction of stainless steel handrails, internal painting and toilet floor tiling. Installation of doors, windows and glass walls have been completed. Tiling the 1st and 2nd floor are basically completed. It is expected that in September 2019, some additional jobs according to the Owner’s request will be completed.