Update construction progress of Textile dyeing and garment factory project– Ramatex Nam Dinh in September 2019

By the end of September 2019, INVESTCORP has completed the entire construction work at the dyeing workshop and handed it to the Owner to implement installation of the machine.

At the textile area, INVESTCORP has completed the construction of drop ceilings, toilet partitions and internal paint. It is expected that in October 2019, the external wall painting will be completed.

At the office area, INVESTCORP has completed the steps’ tiling, completed the installation of doors, windows and stainless steel railings. According to the plan in October 2019, INVESTCORP will complete the external wall paint and execute some additional tasks as requested by the Owner.