At the end of January 2021, the entire warehouse item at Textile dyeing and garment factory project – Ramatex Nam Dinh phase 2 was completed and handed over to the Investor to put into use.
The Main factory and Canteen have been completed and are in the process of industrial cleaning, internal acceptance before acceptance with the Investor.
The roofing of the Parking house will be completed by INVESTCORP on January 31, 2021. It is expected that the Parking house and other outdoor items such as the concrete road, fence, gate and guard house will be completed on February 7, 2021.
Other news
- Autoliv’s Chairman visits and works at the Autoliv Vietnam Factory project – Amata Song Khoai Industrial Park – Quang Yen Town – Quang Ninh Province
- Announcement of Holiday schedule for Apr 30 and May 1, 2024
- Discussion program to celebrate the 114th anniversary of International Women′s Day March 8
- Groundbreaking ceremony of Jehong Textile Factory Project
- Enjoy spring of the new year Giap Thin 2024
- INVESTCORP Group begins the Spring of the Dragon year 2024
- INVESTCORP Group organizes the Year-End Party 2023 – Happy New Year 2024
- Announcement of Tet Holiday 2024
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED