Update construction progress of Textile dyeing and garment factory project – Ramatex Nam Dinh phase 2 in Mar 2020

By the end of Mar 2020, INVESTCORP had completed all piling work of the main factory and auxiliary houses, completed 95% of concrete work of the pipe cap, foundation bracing and completed 80% leveling work of the main factory.

As expected, all of the bracing and pile cap concrete will be finished by Apr 5, 2020 and on Apr 10, 2020, sand levelling work of the main factory will be done. The foundation concrete of the 1st floor will be completed by Apr 15, 2020.