Update construction progress of Vietnam Mie factory project phase 2 in Feb 2019
In Feb 2019, INVESTCORP finished 50% of the foundation framework, beam and bracing at the workshop of the Vietnam Mie factory project phase 2. All construction stages are inspected by the Owner before moving to next steps.
Auxiliary items such as signal boards and internal rules have been finished. Piling work for construction of the water tank is started implementing.
It is expected that in Mar 2019, the foundation items, water tank, brickwork and drainage system will be started implementing.
Other news
- Autoliv’s Chairman visits and works at the Autoliv Vietnam Factory project – Amata Song Khoai Industrial Park – Quang Yen Town – Quang Ninh Province
- Announcement of Holiday schedule for Apr 30 and May 1, 2024
- Discussion program to celebrate the 114th anniversary of International Women′s Day March 8
- Groundbreaking ceremony of Jehong Textile Factory Project
- Enjoy spring of the new year Giap Thin 2024
- INVESTCORP Group begins the Spring of the Dragon year 2024
- INVESTCORP Group organizes the Year-End Party 2023 – Happy New Year 2024
- Announcement of Tet Holiday 2024
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED