Update construction progress of Wearing apparels manufacturing project – Ramatex Hai Phong in December 2017

The Wearing apparels manufacturing project – Ramatex Hai Phong in December 2018 is still implemented as the overall progress of the project by INVESTCORP.

By the end of December 2017, at Block 1, 20,000m2 of the slab and beam concrete of the production buildings No.1&2 and office building were casted counting 40% of the total Block’s concrete volume. At present, INVESTCORP is carrying out the civil work of the Block 1. Along with construction of the civil work, the whole fence system, signal system and perspective posters of the project have been completed.

At Block 2, mass piling work is being carried out simultaneously with excavation and construction of the foundation. Temporary works such as electrical system, lighting system, toilets and rainwater drainage system are being completed urgently for the foundation work.

As expectation, INVESTCORP will continue to speed up progress of the slabs and beams of the Block 1 and foundation of the Block 2 in the following month.

Other news