Update construction progress – Star Villas project in May 2021
In May 2021, INVESTCORP Myanmar focused on building and completing the roof structure of Villas 6, 7, 8, 9, 11; speeding the construction of concrete frame structure of Villa No. 10, 15, 16 and foundation structure of Villa No. 1A, 1B.
At present, INVESTCORP Myanmar is focusing on finishing plastering work for Villas No. 3, 6, 7, 8, 9, 10, 11, 14 and starting to construct gypsum ceiling frames for Villas No. 7, 8, 9.
It is expected that in June 2021, INVESTCORP Myanmar will continue to promote the construction of concrete structures of Villas No. 10, 15, 16, 1A, 1B, construction of roof structures of Villas No. 10, 12, 16 and also continue to promote the construction of plastering and gypsum ceilings of Villas No. 6, 7, 8, 9, 11, 14.
In parallel with the promotion of main works, the outdoor system will also be speeded by INVESTCORP Myanmar in June 2021 such as completing the remaining fence and the drainage system outside the house of Villas No. 3, 6, 7, 8, 9, 11.
Although the political situation is still not completely stable, INVESTCORP Myanmar still tries to ensure the implementation of the project to hand over to the Investor on schedule.
- Autoliv’s Chairman visits and works at the Autoliv Vietnam Factory project – Amata Song Khoai Industrial Park – Quang Yen Town – Quang Ninh Province
- Announcement of Holiday schedule for Apr 30 and May 1, 2024
- Discussion program to celebrate the 114th anniversary of International Women′s Day March 8
- Groundbreaking ceremony of Jehong Textile Factory Project
- Enjoy spring of the new year Giap Thin 2024
- INVESTCORP Group begins the Spring of the Dragon year 2024
- INVESTCORP Group organizes the Year-End Party 2023 – Happy New Year 2024
- Announcement of Tet Holiday 2024