Update construction progress – Suga International (Vietnam) Factory project in February 2021

At the end of February 2021, INVESTCORP has completed the corrugated iron roof of the factory, completed the erection of the exterior panel walls and 90% of the plastering of the Factory and Office of Suga International Factory (Vietnam) project. At present, INVESTCORP is continuing to construct indoor finishing items such as gypsum ceilings and walls, panel ceilings and walls, foundation paint, paintwork and fire protection system.

In the Parking and Canteen area, INVESTCORP has completed the structural items and continues to implement finishing works such as plastering, tiling and painting.

For the outdoor and auxiliary items, INVESTCORP has completed the construction of the water tank system, the wastewater treatment tank while continuing to construct the outdoor drainage and the internal road system. The main gate, secondary gate and guardhouse are also continuing to be implemented.