Update construction progress – Suga International (Vietnam) Factory project in January 2021

At the end of January 2021, at the Factory and Office area of Suga International (Vietnam) factory project, INVESTCORP completed all the erection of steel structures and painting of concrete ceiling on the second floor, completing 90% of the wall construction, 80% of the internal plastering and 20% of the tiling. Exterior panel frame system has been completed and is about to move to construct paneling, gypsum ceiling and floor painting.

At present, INVESTCORP has completed the main structure and steel structure of the Parking house, completed the wastewater treatment system and the fencing work around the factory, completed 30% of the outdoor drainage system and 20% of the road mold for the internal traffic system and connecting to the industrial zone roads...