Update construction progress – Suga International (Vietnam) Factory project in November 2020
In November 2020, at the main Factory and Office of the Suga International (Vietnam) Factory project, INVESTCORP has completed all foundation, ground, and columns at the 1st floor and completed 30% construction work of the 2nd floor.
Parking house and Canteen are executed in parallel and have been completed 70% of the foundation and levelling work.
Regarding outdoor and auxiliary items, INVESTCORP has completed construction of the wastewater treatment tank, casting of walls of domestic water tank and fire tank; casting of guardhouse‘s roof at main gate and completed 70% of surrounding fence.
Other news
- Announcement of Holiday schedule for Apr 30 and May 1, 2024
- Autoliv’s Chairman visits and works at the Autoliv Vietnam Factory project – Amata Song Khoai Industrial Park – Quang Yen Town – Quang Ninh Province
- Discussion program to celebrate the 114th anniversary of International Women′s Day March 8
- Groundbreaking ceremony of Jehong Textile Factory Project
- Enjoy spring of the new year Giap Thin 2024
- INVESTCORP Group begins the Spring of the Dragon year 2024
- INVESTCORP Group organizes the Year-End Party 2023 – Happy New Year 2024
- Announcement of Tet Holiday 2024
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED