Update construction progress – Traditional building project of Tho Xuan district in April 2020

In April 2020, INVESTCORP Land Thanh Hoa completed the construction of plastering works on both sides of the stairs, completed 98% of the gypsum ceiling inside the building and erected 95% of aluminum and glazing works.

Currently, INVESTCORP Land Thanh Hoa is carrying out floor tiles and paving stone on both side of the stairs, completing a number of additional works such as installing the building's nameplates, constructing the lobby and three-step staircase, completing the lighting system, fire protection system, erection of stair railing and glass protection railing...