Update construction progress – Traditional building project of Tho Xuan district in Dec 2019

At the end of Dec 2019, INVESTCORP Land Thanh Hoa completed the foundation work and underground tank. Concrete works of the 1st floor columns and 2nd floor columns were also done.

At present, the assembly of the formwork, reinforcement and pretension cables at the 3rd floor are also being carried out.

As expectation in Jan 2020, INVESTCORP Land Thanh Hoa will accelerated construction of the floor and ceiling concrete.

Other news