Update construction progress – Traditional building project of Tho Xuan district in January 2020
By the end of Jan 2020, INVESTCORP Land Thanh Hoa has completed floor concrete of the 2nd floor, 3rd floor and 4th floor of the Traditional building project of Tho Xuan district, ensuring safety, quality, and progress as per requirement.
As expectation in Feb 2020, INVESTCORP Land Thanh Hoa will complete inspection of the floor cable tension of the 4th floor and insert grout into the pre-stressed cables; dismantle all formworks of the 2nd floor and 3rd floor. Casting column concrete and attic concrete at two sides of the staircases are executed in parallel brickwork and plastering of the whole building.
Other news
- Autoliv’s Chairman visits and works at the Autoliv Vietnam Factory project – Amata Song Khoai Industrial Park – Quang Yen Town – Quang Ninh Province
- Announcement of Holiday schedule for Apr 30 and May 1, 2024
- Discussion program to celebrate the 114th anniversary of International Women′s Day March 8
- Groundbreaking ceremony of Jehong Textile Factory Project
- Enjoy spring of the new year Giap Thin 2024
- INVESTCORP Group begins the Spring of the Dragon year 2024
- INVESTCORP Group organizes the Year-End Party 2023 – Happy New Year 2024
- Announcement of Tet Holiday 2024
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED