Update construction progress – Traditional building project of Tho Xuan district in January 2020

By the end of Jan 2020, INVESTCORP Land Thanh Hoa has completed floor concrete of the 2nd floor, 3rd floor and 4th floor of the Traditional building project of Tho Xuan district, ensuring safety, quality, and progress as per requirement.

As expectation in Feb 2020, INVESTCORP Land Thanh Hoa will complete inspection of the floor cable tension of the 4th floor and insert grout into the pre-stressed cables; dismantle all formworks of the 2nd floor and 3rd floor. Casting column concrete and attic concrete at two sides of the staircases are executed in parallel brickwork and plastering of the whole building.