Update construction progress - Yukioh factory project in April 2020

By the end of April 2020, the factory and office building area of the Yukioh factory project continued to be carried out the rest finishing items by INVESTCORP Myanmar such as erecting ceiling panels, painting finishing...

The power room, pump room, water tanks and wastewater treatment tanks were handed over to the Owner to install the equipment. The auxiliary items such as security house, external toilet, additional foundation and light load road are also being completed and will be handed over on May 12, 2020 as scheduled.

It is expected that in May 2020, INVESTCORP Myanmar will execute and complete the items of grass planting, interlocking tiles, leveling and all other items of the project to hand over to the Owner.