Update construction progress - Yukioh factory project in April 2020
By the end of April 2020, the factory and office building area of the Yukioh factory project continued to be carried out the rest finishing items by INVESTCORP Myanmar such as erecting ceiling panels, painting finishing...
The power room, pump room, water tanks and wastewater treatment tanks were handed over to the Owner to install the equipment. The auxiliary items such as security house, external toilet, additional foundation and light load road are also being completed and will be handed over on May 12, 2020 as scheduled.
It is expected that in May 2020, INVESTCORP Myanmar will execute and complete the items of grass planting, interlocking tiles, leveling and all other items of the project to hand over to the Owner.

Other news
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police
- INVESTCORP Group Organizes Annual Employee Health Check-up Program 2025
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED