Update construction progress – Yukioh factory project in Aug 2019
By the end of August 2019, INVESTCORP Myanmar has completed site clearance and construction of temporary items for the Yukioh Factory project including roads, fences, gates etc.
At present, the foundation work of the main workshop area and the office building are being speeded up. The internal road of the workshop area has also started to be implemented.
It is expected that in September 2019, INVESTCORP Myanmar will continue to speed up the construction of the foundation system of the main workshop, office building and internal road system. The main gate, sedimentation tanks, septic tanks, water tanks, collection pits and a number of other items will also be implemented simultaneously to ensure the progress of the Owner.
Other news
- Congratulations to VDL ETG Group (Netherlands) on inauguration of its first factory in Vietnam
- INVESTCORP Group welcomes and works with the delegation from the German Chamber of Commerce and Industry (IHK) Region Stuttgart
- Groundbreaking Ceremony of staBOO Thanh Hoa OSB Bamboo Board Manufacturing Plant
- Announcement of Holiday schedule for Apr 30 and May 1, 2025
- Seminar to celebrate International Women′s Day March 8
- Spring travel of At Ty 2025
- INVESTCORP Group opens the spring of year At Ty 2025
- Year-end Ceremony 2024 - Welcoming the New Year 2025
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED