Update construction progress – Yukioh factory project in Aug 2019
By the end of August 2019, INVESTCORP Myanmar has completed site clearance and construction of temporary items for the Yukioh Factory project including roads, fences, gates etc.
At present, the foundation work of the main workshop area and the office building are being speeded up. The internal road of the workshop area has also started to be implemented.
It is expected that in September 2019, INVESTCORP Myanmar will continue to speed up the construction of the foundation system of the main workshop, office building and internal road system. The main gate, sedimentation tanks, septic tanks, water tanks, collection pits and a number of other items will also be implemented simultaneously to ensure the progress of the Owner.
Other news
- Autoliv’s Chairman visits and works at the Autoliv Vietnam Factory project – Amata Song Khoai Industrial Park – Quang Yen Town – Quang Ninh Province
- Discussion program to celebrate the 114th anniversary of International Women′s Day March 8
- Groundbreaking ceremony of Jehong Textile Factory Project
- Enjoy spring of the new year Giap Thin 2024
- INVESTCORP Group begins the Spring of the Dragon year 2024
- INVESTCORP Group organizes the Year-End Party 2023 – Happy New Year 2024
- Announcement of Tet Holiday 2024
- Groundbreaking ceremony of Heritage Food Vietnam Factory Project
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED