Update construction progress – Yukioh factory project in Aug 2019

By the end of August 2019, INVESTCORP Myanmar has completed site clearance and construction of temporary items for the Yukioh Factory project including roads, fences, gates etc.

At present, the foundation work of the main workshop area and the office building are being speeded up. The internal road of the workshop area has also started to be implemented.

It is expected that in September 2019, INVESTCORP Myanmar will continue to speed up the construction of the foundation system of the main workshop, office building and internal road system. The main gate, sedimentation tanks, septic tanks, water tanks, collection pits and a number of other items will also be implemented simultaneously to ensure the progress of the Owner.