Update construction progress – Yukioh factory project in December 2019
In Dec 2019, INVESTCORP Myanmar basically completed brick walls and prepared construction of finishing work, tiling, ceiling and partitions of the office. Concrete work of the factory also completed 80%. Currently, INVESTCORP Myanmar is moving to brickwork of the factory.
Auxiliary items such as light load road continues to be implemented as per schedule and will be completed 50% in Jan 2020. Wastewater treatment has been completed underground concrete work and is executed formwork and the reinforcement above the ground.
The fence is constructed the foundation and beam by INVESTCORP Myanmar in parallel with fabrication of the fence frame.
Other news
- Congratulations to VDL ETG Group (Netherlands) on inauguration of its first factory in Vietnam
- INVESTCORP Group welcomes and works with the delegation from the German Chamber of Commerce and Industry (IHK) Region Stuttgart
- Groundbreaking Ceremony of staBOO Thanh Hoa OSB Bamboo Board Manufacturing Plant
- Announcement of Holiday schedule for Apr 30 and May 1, 2025
- Seminar to celebrate International Women′s Day March 8
- Spring travel of At Ty 2025
- INVESTCORP Group opens the spring of year At Ty 2025
- Year-end Ceremony 2024 - Welcoming the New Year 2025
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED