Update construction progress - Yukioh factory project in Feb 2020
By the end of Feb 2020, plastering work of the surrounding walls and construction of the ground for the main factory of the Yukioh factory project have completed. At present, INVESTCORP Myanmar is carrying out gypsum partitions, barriers inside the factory and continues execute finishing work of the office building.
Auxiliary items such as wastewater treatment tanks have been completion of structure and is being implemented finishing work. Pump room and power room are also completed concrete structure, plastering and brickwork and carried out roof erection.
It is expected that in March 2020, INVESTCORP Myanmar will complete the wastewater treatment tanks, speed up machine foundation, light load road and complete the new wastewater treatment tank.
- Autoliv’s Chairman visits and works at the Autoliv Vietnam Factory project – Amata Song Khoai Industrial Park – Quang Yen Town – Quang Ninh Province
- Announcement of Holiday schedule for Apr 30 and May 1, 2024
- Discussion program to celebrate the 114th anniversary of International Women′s Day March 8
- Groundbreaking ceremony of Jehong Textile Factory Project
- Enjoy spring of the new year Giap Thin 2024
- INVESTCORP Group begins the Spring of the Dragon year 2024
- INVESTCORP Group organizes the Year-End Party 2023 – Happy New Year 2024
- Announcement of Tet Holiday 2024