Update construction progress - Yukioh factory project in Feb 2020

By the end of Feb 2020, plastering work of the surrounding walls and construction of the ground for the main factory of the Yukioh factory project have completed. At present, INVESTCORP Myanmar is carrying out gypsum partitions, barriers inside the factory and continues execute finishing work of the office building.

Auxiliary items such as wastewater treatment tanks have been completion of structure and is being implemented finishing work. Pump room and power room are also completed concrete structure, plastering and brickwork and carried out roof erection.

It is expected that in March 2020, INVESTCORP Myanmar will complete the wastewater treatment tanks, speed up machine foundation, light load road and complete the new wastewater treatment tank.