Update construction progress – Yukioh factory project in Nov 2019
In Nov 2019, INVESTCORP Myanmar executed plastering work of the office, formwork, rebar and ground concrete of the workshop. The entire internal road of heavy load, foundation of the wastewater treatment tanks and Pit system have been completed.
At present, INVESTCORP Myanmar is carrying out light load road, executing fence foundation and fabrication of fence frame.
In Dec 2019, INVESTCORP Myanmar will speed up execution of the wastewater treatment tanks, water tanks and other auxiliary tanks; finish of drainage system etc.
Other news
- Autoliv’s Chairman visits and works at the Autoliv Vietnam Factory project – Amata Song Khoai Industrial Park – Quang Yen Town – Quang Ninh Province
- Discussion program to celebrate the 114th anniversary of International Women′s Day March 8
- Groundbreaking ceremony of Jehong Textile Factory Project
- Enjoy spring of the new year Giap Thin 2024
- INVESTCORP Group begins the Spring of the Dragon year 2024
- INVESTCORP Group organizes the Year-End Party 2023 – Happy New Year 2024
- Announcement of Tet Holiday 2024
- Groundbreaking ceremony of Heritage Food Vietnam Factory Project
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED