Update construction progress – Yukioh factory project in Oct 2019

By the end of Oct 2019, at the main workshop, INVESTCORP Myanmar has been carrying out assembly of main structure, sand levelling and workshop’s ground compact. At the office area, assembly of main structure is also executed in parallel with the fabrication of formwork and assembly of ground reinforcement.

Currently, INVESTCORP Myanmar continues executing and completing the internal road of heavy load and prepare to implement the light load one. The foundation excavation, pile head cutting, reinforcement fabrication of the drainage system and the factory water tanks are in progress.

It is expected that in November 2019, INVESTCORP Myanmar will accelerate the construction of wastewater treatment system, water tanks and other auxiliary tanks; constructing drainage ditch system etc.