Construction progress updated in October 2023 – Autoliv Vietnam project

In October 2013, INVESTCORP completed 100% of the temporary items and static compression test piles.

For Factory 1, mass pile pressing reached 3% of the volume and 45% of the land leveling. For Factory 2, mass pile pressing reached 35% of the volume and 85% of the land leveling.
For the Office building, mass pile pressing work completed 15% of the volume and 70% of the land leveling volume. Mass pile pressing work for the ancillary items is 80% complete.

It is expected that in November 2023, INVESTCORP will continue to accelerate the construction progress of mass pile pressing, land leveling, excavation of foundation holes, construction of formwork, reinforcement, and pouring concrete for foundation stations and bracing foundations at Factory 1&2, construction of office buildings, underground water tanks, and other ancillary items.