Update construction progress of New warehouse project – Peony factory in February 2021
In February 2021, INVESTCORP has completed the construction of concrete foundation, completed the construction of the roads and the outdoor rainwater drainage system at the New warehouse project - Peony Factory.
Update construction progress – Multifunctional house of Tho Xuan High school No 4, Tho Xuan district in February 2021
At the end of February 2021, INVESTCORP Land Thanh Hoa continued to construct the brickwork of the multifunctional house’s structure. The volume of the works done in the month includes fabrication and erection of formwork, reinforcement, concreting of curved roof beams cos + 9.80m and fabrication of steel structure at the factory.
Update construction progress in February 2021 – Dong Nam Residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province
In February 2021, INVESTCORP Land Thanh Hoa carried out the construction of concrete structures for drainage systems; construction and installation of sewers, building manholes to collect surface water and gathering macadam to the site.
Update construction progress – Suga International (Vietnam) Factory project in February 2021
At the end of February 2021, INVESTCORP has completed the corrugated iron roof of the factory, completed the erection of the exterior panel walls and 90% of the plastering of the Factory and Office of Suga International Factory (Vietnam) project. At present, INVESTCORP is continuing to construct indoor finishing items such as gypsum ceilings and walls, panel ceilings and walls, foundation paint, paintwork and fire protection system.
Update construction progress – Lakeside Service Apartment (Myanmar) project, Star Villas project and Norman Myanmar factory project in January 2021
Due to the influence of the military coup on February 1, 2021, all projects in Myanmar including Lakeside Service Apartment (Myanmar) project, Star Villas project and Norman Myanmar factory project had to be suspended to ensure safety for all employees of INVESTCORP Myanmar and subcontractors working in the projects.
Update construction progress of Textile dyeing and garment factory project – Ramatex Nam Dinh phase 2 in February 2021
In February 2021, INVESTCORP completed all the indoor work items to carry out inspection and handover of each part to the Investor.
Update construction progress of New warehouse project – Peony factory in January 2021
The new warehouse project - Peony factory was commenced on December 1, 2020 with an area of 1760 m2 in the form of steel-frame house, corrugated iron walls combined with 1m high walls and concrete ground.
Update construction progress of Norman Myanmar factory project in January 2021
The Norman Myanmar factory project was started on January 10, 2021 by INVESTCORP Myanmar in Zone B - Thilawa Special economic zone.
Update construction progress – Multifunctional house of Tho Xuan High school No 4, Tho Xuan district in January 2021
In January 2021, INVESTCORP Land Thanh Hoa focused on the construction of the Multi-functional house’s structure. The works that have been done in the month include the concrete work of the slab and beam on the 2nd floor cos + 4.8m, construction of formwork and reinforcement, pouring concrete on the 2nd floor, completion of building brick walls on the 2nd floor to cos + 9.8m and the fabrication of steel frame roof at the factory.
Update construction progress in January 2021 – Dong Nam Residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province
At the end of January 2021, INVESTCORP Land Thanh Hoa continued constructing and completing the compaction of K95 soil on the sidewalk, casting drainage structures and gathering macadam to the site. At present, INVESTCORP Land Thanh Hoa is constructing and installing drainage culverts on the roads.
Update construction progress – Lakeside Service Apartment (Myanmar) project in January 2021
In January 2021, INVESTCORP Myanmar has completed all reinforced concrete structures of the basement ground and slab and continues implementing other works at the basement such as pouring wall reinforced concrete, waterproofing of the walls’ external surface, sand filling and disassembly of pile support system.
Update construction progress – Suga International (Vietnam) Factory project in January 2021
At the end of January 2021, at the Factory and Office area of Suga International (Vietnam) factory project, INVESTCORP completed all the erection of steel structures and painting of concrete ceiling on the second floor, completing 90% of the wall construction, 80% of the internal plastering and 20% of the tiling. Exterior panel frame system has been completed and is about to move to construct paneling, gypsum ceiling and floor painting.
Update construction progress – Star Villas project in January 2021
In January 2021, INVESTCORP Myanmar completed and handed over the Villa No. 5 to the Investor for use on January 20, 2021 according to the expected schedule.
Update construction progress of Textile dyeing and garment factory project – Ramatex Nam Dinh phase 2 in January 2021
At the end of January 2021, the entire warehouse item at Textile dyeing and garment factory project – Ramatex Nam Dinh phase 2 was completed and handed over to the Investor to put into use.