Construction progress updated in April 2023 – Dai Lai Eco-Residence and Resort Project, Ngoc Thanh Commune, Phuc Yen City, Vinh Phuc Province

Construction progress updated in April 2023 – Dai Lai Eco-Residence and Resort Project, Ngoc Thanh Commune, Phuc Yen City, Vinh Phuc Province

At the end of April 2023, IVC Creation Company constructed and basically completed the package "Construction of sidewalks curbs and paving stones". Items constructed by IVC Creation in the month included concrete pavement construction and installation of curbs and paving stones.
Construction progress updated in April 2023 – Residential Area Technical Infrastructure Project in Quang Dong Commune, Thanh Hoa City, Thanh Hoa Province

Construction progress updated in April 2023 – Residential Area Technical Infrastructure Project in Quang Dong Commune, Thanh Hoa City, Thanh Hoa Province

In April 2023, INVESTCORP Land Thanh Hoa mobilized machinery and labor to implement the items of the contract.    
Construction progress updated in April 2023 – Typical Residential Area Infrastructure Project in Hoang Hoc Village, Dong Hoang Commune, Dong Son District, Thanh Hoa Province

Construction progress updated in April 2023 – Typical Residential Area Infrastructure Project in Hoang Hoc Village, Dong Hoang Commune, Dong Son District, Thanh Hoa Province

At the end of April 2023, INVESTCORP Land Thanh Hoa basically completed the construction of roads and campus items.
Construction progress updated in April 2023 - Renovation and upgrading project of provincial road 506B, section from Tho Lap commune to Xuan Tin commune, Tho Xuan district

Construction progress updated in April 2023 - Renovation and upgrading project of provincial road 506B, section from Tho Lap commune to Xuan Tin commune, Tho Xuan district

In April 2023, INVESTCORP Land Thanh Hoa mobilized machinery and human resources to carry out the construction of the items and workload according to the contract.
Construction progress updated in April 2023 – Road project from Xuan Hung commune connecting with road from Tho Xuan town to Lam Son – Sao Vang urban area, Tho Xuan district

Construction progress updated in April 2023 – Road project from Xuan Hung commune connecting with road from Tho Xuan town to Lam Son – Sao Vang urban area, Tho Xuan district

In April 2023, INVESTCORP Land Thanh Hoa basically completed the works in the traffic category, including the construction of macadam for road surface reached 100%, and asphalt pavement construction reached 100%.
Construction progress updated in April 2023 - Project of renovating and upgrading rescue road in Truong Xuan commune to left dike of Chu River, Tho Xuan district, Thanh Hoa province

Construction progress updated in April 2023 - Project of renovating and upgrading rescue road in Truong Xuan commune to left dike of Chu River, Tho Xuan district, Thanh Hoa province

In April 2023, INVESTCORP Land Thanh Hoa Company completed the construction of items, including drainage, installation of electrical equipment, and construction of macadam, and asphalt pavement. Total construction output is estimated at 50% of the project volume.
Construction progress updated in March 2023 – Key Technology Hanoi Factory Project Phase 2

Construction progress updated in March 2023 – Key Technology Hanoi Factory Project Phase 2

By the end of March 2023, INVESTCORP 9 has completed 60% of the project's workload, including backfilling and lining for the factory floor reached 60%, plastering the factory wall reached 90%; completed 100% of the foundation base and house column painting; completed concrete pouring of the foundation floor and erected steel columns for the garbage house; completed steel erection and roof beam formwork.
Construction progress updated in March 2023 - Vina Ito Factory Project Phase 2

Construction progress updated in March 2023 - Vina Ito Factory Project Phase 2

In March 2023, INVESTCORP 15 completed pouring concrete of the factory floor; along with that, tiling the toilet area of the factory, installing curbs, completing manholes, and completing garbage houses were also completed.
Construction progress updated in March 2023 - TOYO INK COMPOUNDS Vietnam Factory Project Phase 3

Construction progress updated in March 2023 - TOYO INK COMPOUNDS Vietnam Factory Project Phase 3

At the end of March 2023, INVESTCORP 10 has completed the pile pressing works for the main factory, warehouse and powerhouse.
Groundbreaking Ceremony of Urban Renovation Project in Sao Vang town, Tho Xuan district; Item: Lighting system for Nguyen Mau Tuyen, Trinh Khac Phuc, Tran Hoanh streets and road from Xuan Long to Xuan Hop

Groundbreaking Ceremony of Urban Renovation Project in Sao Vang town, Tho Xuan district; Item: Lighting system for Nguyen Mau Tuyen, Trinh Khac Phuc, Tran Hoanh streets and road from Xuan Long to Xuan Hop

On the afternoon of February 28, 2023, Tho Xuan district held the groundbreaking ceremony of the Urban Renovation Project in Sao Vang town, Tho Xuan district; Item: Lighting system for Nguyen Mau Tuyen, Trinh Khac Phuc, Tran Hoanh streets and road from Xuan Long to Xuan Hop. The project is invested by the People's Committee of Sao Vang town for the purpose of public lighting to ensure security and social order, as well as the lives of people in the area.
Construction progress updated in March 2023 – Dai Lai Eco-Residence and Resort Project, Ngoc Thanh Commune, Phuc Yen City, Vinh Phuc Province

Construction progress updated in March 2023 – Dai Lai Eco-Residence and Resort Project, Ngoc Thanh Commune, Phuc Yen City, Vinh Phuc Province

By the end of March 2023, IVC Creation has completed the work items under the "Construction of earth retaining wall" package. During the month, the Company has completed 100% of the erection works of reinforcement, formwork and concrete pouring of retaining walls, construction of backfilling.
Construction progress updated in March 2023 – Road project from Xuan Hung commune connecting with road from Tho Xuan town to Lam Son – Sao Vang urban area, Tho Xuan district

Construction progress updated in March 2023 – Road project from Xuan Hung commune connecting with road from Tho Xuan town to Lam Son – Sao Vang urban area, Tho Xuan district

In March 2023, INVESTCORP Land Thanh Hoa completed the construction of crushed stone and asphalted the road surface, and completed the installation of the drainage system. Total output is estimated at 67% of the contract volume.
Construction progress updated in March 2023 - Project of renovating and upgrading rescue road in Truong Xuan commune to left dike of Chu river, Tho Xuan district, Thanh Hoa province

Construction progress updated in March 2023 - Project of renovating and upgrading rescue road in Truong Xuan commune to left dike of Chu river, Tho Xuan district, Thanh Hoa province

In March 2023, the construction of soil excavation, crushed stone, concrete formwork, K98 compaction, and concrete pouring to return the drainage ditch were 100% completed by INVESTCORP Land Thanh Hoa. At the same time, the work of digging and spreading underground cables to install electrical equipment, the construction of macadam and road asphalt have also been completed. Total construction output is estimated at 49% of the contract volume.
Construction progress updated in March 2023 – Sao Mai Resort Project, Tho Lam Commune – Tho Xuan District – Thanh Hoa Province

Construction progress updated in March 2023 – Sao Mai Resort Project, Tho Lam Commune – Tho Xuan District – Thanh Hoa Province

In March 2023, INVESTCORP 6 continued to construct items, including reception house, Rubby Four Seasons villa area, Bungalow under the lake and other ancillary items.