Construction progress updated in July 2023 – Residential Area Technical Infrastructure Project in Quang Dong commune, Thanh Hoa city

Construction progress updated in July 2023 – Residential Area Technical Infrastructure Project in Quang Dong commune, Thanh Hoa city

By the end of July 2023, INVESTCORP Land Thanh Hoa has performed over 80% of the transport category including the embankment of the K95 soil road reached 83%, the embankment of the K98 soil road reached 91% and the construction of crushed stone foundation type II reached 90%, crushed stone foundation type I reached 80%. For the drainage system, the Company has also implemented the installation of sewers D600 and D400 reached 95% of the contract volume.
Construction progress updated in July 2023 – Typical Residential Area Infrastructure Project in Hoang Hoc Village, Dong Hoang Commune, Dong Son District, Thanh Hoa Province

Construction progress updated in July 2023 – Typical Residential Area Infrastructure Project in Hoang Hoc Village, Dong Hoang Commune, Dong Son District, Thanh Hoa Province

In July 2023, INVESTCORP Land Thanh Hoa focused on completing the remaining items in the contract, including the construction of additional roads reached 100%; the construction of the drainage system and the bricklaying work reached 100% of the volume. Total cumulative construction volume reached 100%.
Construction progress updated in July 2023 - Project of renovating and upgrading rescue road in Truong Xuan commune to left dike of Chu River, Tho Xuan district, Thanh Hoa province

Construction progress updated in July 2023 - Project of renovating and upgrading rescue road in Truong Xuan commune to left dike of Chu River, Tho Xuan district, Thanh Hoa province

In July 2023, INVESTCORP Land Thanh Hoa basically completed the drainage system, installed the lighting system, and completed the construction of crushed stone and spread asphalt for the road surface. Total construction output is estimated at 50% of the contract volume.
Construction progress updated in July 2023 - Renovation and upgrading project of provincial road 506B, section from Tho Lap commune to Xuan Tin commune, Tho Xuan district

Construction progress updated in July 2023 - Renovation and upgrading project of provincial road 506B, section from Tho Lap commune to Xuan Tin commune, Tho Xuan district

In July 2023, INVESTCORP Land Thanh Hoa continued to carry out works including excavation and transportation of weathered soil reached 63%; transportation and embankment of K95 reached 80%; construction of intersections and crossroads reached 10%; construction of horizontal culverts reached 12%.
Construction progress updated in June 2023 - TOYO INK COMPOUNDS Vietnam Factory Project Phase 3

Construction progress updated in June 2023 - TOYO INK COMPOUNDS Vietnam Factory Project Phase 3

At the end of June 2023, INVESTCORP 10 completed the floor beams on the 3rd floor of the factory area and is proceeding with the construction of plastering of the 1st floor, and painting of the ceiling beams of the 2nd floor. The Company has also carried out connection work and roofing of the warehouse, and painting the powerhouse.
Construction progress updated in June 2023 – Key Technology Hanoi Factory Project Phase 2

Construction progress updated in June 2023 – Key Technology Hanoi Factory Project Phase 2

By the end of June 2023, INVESTCORP 9 has completed 98% of the whole project, the completed items include the factory, paint house, motorbike parking house, and ancillary houses (parking house, garbage house, water tank, and pump house).
Construction progress updated in June 2023 – An additional package of

Construction progress updated in June 2023 – An additional package of "Parking house - Garbage house - Chemical warehouse" under "Textile and Garment Factory Project of Ramatex Nam Dinh- Phase 1"

At the end of June 2023, INVESTCORP 15 completed the construction of the parking house and carried out the repair, acceptance, and handover to the Investor.
Construction progress updated in May 2023 – Sao Mai Resort Project, Tho Lam Commune – Tho Xuan District – Thanh Hoa Province

Construction progress updated in May 2023 – Sao Mai Resort Project, Tho Lam Commune – Tho Xuan District – Thanh Hoa Province

In June 2023, INVESTCORP 6 completed constructing the structure and plastering the reception area. The tennis court and laundry area have also been completed by INVESTCORP 6 and are finishing the interior for acceptance. At the Family villa area, INVESTCORP 6 is implementing the construction of floor beams and structures.
Construction progress updated in June 2023 – Residential Area Technical Infrastructure Project in Quang Dong Commune, Thanh Hoa City, Thanh Hoa Province

Construction progress updated in June 2023 – Residential Area Technical Infrastructure Project in Quang Dong Commune, Thanh Hoa City, Thanh Hoa Province

In June 2023, INVESTCORP Land Thanh Hoa completed 83% of the K95 soil road embankment, 91% of the K98 embankment, 90% of the type II macadam foundation, and 80% of the type I macadam one. At the same time, the installation of the drainage system was also completed at 95% of the volume, and the construction of the curb reached 85%.
Construction progress updated in June 2023 – Road project from Xuan Hung commune connecting with road from Tho Xuan town to Lam Son – Sao Vang urban area, Tho Xuan district

Construction progress updated in June 2023 – Road project from Xuan Hung commune connecting with road from Tho Xuan town to Lam Son – Sao Vang urban area, Tho Xuan district

In June 2023, INVESTCORP Land Thanh Hoa completed the construction of the roads. The works such as the construction of crossroads reached 100%, and the construction of traffic safety system reached 100%. Total output is estimated at 100% of the contract.
Construction progress updated in June 2023 - Project of renovating and upgrading rescue road in Truong Xuan commune to left dike of Chu River, Tho Xuan district, Thanh Hoa province

Construction progress updated in June 2023 - Project of renovating and upgrading rescue road in Truong Xuan commune to left dike of Chu River, Tho Xuan district, Thanh Hoa province

By the end of June 2023, INVESTCORP Land Thanh Hoa has completed 100% of the drainage system, lighting, and road surface items. Total output is estimated at 50% of the volume.
Construction progress updated in June 2023 - Renovation and upgrading project of provincial road 506B, section from Tho Lap commune to Xuan Tin commune, Tho Xuan district

Construction progress updated in June 2023 - Renovation and upgrading project of provincial road 506B, section from Tho Lap commune to Xuan Tin commune, Tho Xuan district

In June 2023, INVESTCORP Land Thanh Hoa focused on implementing the construction of road surfaces and drainage systems.
Construction progress updated in May 2023 – Dai Lai Eco-Residence and Resort Project, Ngoc Thanh Commune, Phuc Yen City, Vinh Phuc Province

Construction progress updated in May 2023 – Dai Lai Eco-Residence and Resort Project, Ngoc Thanh Commune, Phuc Yen City, Vinh Phuc Province

By the end of May 2023, the works in the categories "Construction of earth retaining walls" and "Construction and installation of sidewalk curbs and paving stones" performed by IVC Creation Joint Stock Company have been basically completed.
Construction progress updated in May 2023 - Renovation and upgrading project of provincial road 506B, section from Tho Lap commune to Xuan Tin commune, Tho Xuan district

Construction progress updated in May 2023 - Renovation and upgrading project of provincial road 506B, section from Tho Lap commune to Xuan Tin commune, Tho Xuan district

In May 2023, INVESTCORP Land Thanh Hoa excavated and transported weathered soil with 43% of the work volume; transported and embanked the K95 reached 18% of the volume. For the drainage system, the Company is implementing the construction of horizontal culvert steel.