Construction progress updated in September 2021 – Project of Repairing damage of roadbed, road surface and drainage system section Km3+00 -:- Km10+500, National way 47B, Thanh Hoa province

Construction progress updated in September 2021 – Project of Repairing damage of roadbed, road surface and drainage system section Km3+00 -:- Km10+500, National way 47B, Thanh Hoa province

The project of repairing damaged roadbed, road surface and surface water drainage system of National way 47B, Thanh Hoa province is invested by the Transportation Department of Thanh Hoa province with a total length of nearly 2.5 km, including the following items: repairing road surface, repairing and installing load-bearing drainage system, installing signal system, pickets, painting road markings...
Construction progress updated in September 2021 – Project of route from National way 47C to revolutionary historical site of Mr. Ho Sy Nhan's family, Xuan Hoa commune, Tho Xuan district

Construction progress updated in September 2021 – Project of route from National way 47C to revolutionary historical site of Mr. Ho Sy Nhan's family, Xuan Hoa commune, Tho Xuan district

With the approval of Tho Xuan District People's Committee, INVESTCORP Land Thanh Hoa has implemented the construction of the route from National way 47C to the revolutionary historical site of Mr. Ho Sy Nhan's family in Xuan Hoa commune, Tho Xuan district, Thanh Hoa province. The project has a total length of 1.5km, including the main road 1.3km long and the branch road 0.2km long.
Construction progress updated in September 2021 – Toray International Vietnam factory project in Quang Ngai

Construction progress updated in September 2021 – Toray International Vietnam factory project in Quang Ngai

Toray International Vietnam factory project in Quang Ngai was implemented by INVESTCORP 9 Company at No. 9, Tu Do Boulevard, Vietnam - Singapore Industrial Park, Tinh Tho Commune, Son Tinh District, Quang Ngai Province, Vietnam on the land lot with a total area of 41,403.7m2, including office, factory, canteen, parking, security house...
INVESTCORP Land Thanh Hoa celebrates 3 years of establishment

INVESTCORP Land Thanh Hoa celebrates 3 years of establishment

After 3 years of establishment, all employees of INVESTCORP Land Thanh Hoa Company Limited have always understood the Group's expected goals and always strived every day to complete the assigned tasks. In which, the factors of product quality, building the management system and operating the business in accordance with the local are always the top priorities. Up to now, INVESTCORP Land Thanh Hoa has built an apparatus including 5 member companies, 63 employees/engineers, 5 construction teams, execution of 26 construction projects and 1 real estate project… Projects always receive positive feedback from partners.
Groundbreaking ceremony of Renovation and improvement project of Thanh Quang Park (historical site of lamp factory), Ba Dinh ward, Thanh Hoa city

Groundbreaking ceremony of Renovation and improvement project of Thanh Quang Park (historical site of lamp factory), Ba Dinh ward, Thanh Hoa city

On September 22, 2021, INVESTCORP Land Thanh Hoa held the Groundbreaking ceremony of the Renovation and improvement project of Thanh Quang Park (historical site of lamp factory), Ba Dinh ward, Thanh Hoa city. The ceremony was presented by the Leaders of Project Management Board of construction investment No. 2 - Thanh Hoa city, representatives of Ba Dinh ward, the Board of Directors and the Construction team leaders of INVESTCORP Land Thanh Hoa.
Construction progress updated in September 2021– Manufacturing eco-friendly decor product project

Construction progress updated in September 2021– Manufacturing eco-friendly decor product project

At the end of September 2021, in the office area of the Manufacturing eco-friendly decor product project, INVESTCORP 15 Company has completed the construction of all columns on the 2nd & 3rd floors, floor beam concrete on the 3rd floor, roof and 60% of the wall construction on the 1st floor. The plastering work of the basement is also being carried out in parallel. In the factory area, INVESTCORP 15 has finished plastering the interior and exterior walls and 60% of the concrete lining work.
Construction progress updated in September 2021 – Yi Da Garment Factory Project Phase 3 - Canteen parking

Construction progress updated in September 2021 – Yi Da Garment Factory Project Phase 3 - Canteen parking

At the end of September 2021, INVESTCORP Dong Minh has completed the construction of brickwork and moved to the finishing work of the Yi Da garment factory project - Phase 3 - Canteen parking.
Construction progress updated in September 2021 – Typical Residential Area Infrastructure Project in Hoang Hoc Village, Dong Hoang Commune, Dong Son District, Thanh Hoa Province

Construction progress updated in September 2021 – Typical Residential Area Infrastructure Project in Hoang Hoc Village, Dong Hoang Commune, Dong Son District, Thanh Hoa Province

In September 2021, despite being affected by the Covid-19 pandemic and rainy weather etc., INVESTCORP Land Thanh Hoa Company still overcomes difficulties to implement some work items of the Typical Residential Area Infrastructure Project in Hoang Hoc Village, Dong Hoang Commune, Dong Son District, Thanh Hoa Province. The works performed during the month includes dredging, ground excavation and excavation of roads and embankment of K95 and K98 soils for the foundations of roads No. 1, 2, 3A, 4, 5, 6, 8, 9, 10 & 11 reaching 70% of total workload; precast of concrete structures for drainage and electrical systems.
Construction progress updated in September 2021 – Dong Nam Residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province

Construction progress updated in September 2021 – Dong Nam Residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province

In September 2021, INVESTCORP Land Thanh Hoa continues to construct items related to traffic, sidewalks, green trees and lighting installation. The volume of works achieved in the month includes 98% of road foundation, 70% of sidewalk trees and 80% of lighting works.
Construction progress updated in September 2021 – Star Villas project

Construction progress updated in September 2021 – Star Villas project

In September 2021, INVESTCORP Myanmar continues to promote painting work and drywall ceilings for villas No. 3, 6, 7, 9, 12 & 14. Villas No. 8 and 11 have been handed over to the Investor to install equipment and will be implemented the final finishing works in October 2021.
Construction progress updated in September 2021– Lakeside Service Apartment (Myanmar) project

Construction progress updated in September 2021– Lakeside Service Apartment (Myanmar) project

In September 2021, INVESTCORP Myanmar has completely removed formwork for beams and floor slabs; completed construction of the basement stair structure and completed 100% of the toilet work, completed the entire basement concrete surface and floor slabs of the Lakeside Service Apartment (Myanmar) project to prepare for acceptance, handover in early October 2021. In addition to dismantling, the work of clearing warehouses, gathering materials and leveling the ground were also completed on schedule.
Construction progress updated in August 2021 – Manufacturing eco-friendly decor product project

Construction progress updated in August 2021 – Manufacturing eco-friendly decor product project

At the end of August 2021, at the Manufacturing eco-friendly decor product project, INVESTCORP 15 Company has completed the construction of all columns on the 1st floor, beam and slab concrete on the 2nd floor of the office area and is continuing the construction of internal and external plastering of the walls surrounding the factory area. The bottom and walls of the ditch system in the factory have been completed and will be carry out finishing work together with the ground concrete. Currently, INVESTCORP 15 is starting to implement the lean concrete of the factory floor in parallel with digging, filling the earthing system and compacting the factory floor.
Construction progress updated in August 2021 – Yi Da Garment Factory Project Phase 3 - Canteen & Motorbike parking

Construction progress updated in August 2021 – Yi Da Garment Factory Project Phase 3 - Canteen & Motorbike parking

On June 10, 2021, the Yi Da Garment Factory Project Phase 3 - Canteen & Motorbike parking of Yi Da Vietnam Limited was commenced at Song Thao Industrial Complex, Cam Khe town, Cam Khe district, Phu Tho province. The Canteen & Motorbike parking is built with a 3-storey open space design, a total floor area of 7,140m2 and a building height of 11.35m.
Construction progress updated in August 2021 – Project of Renovation and expansion of main gate, build of reception house combined with installing equipment to manage national database on population of Tho Xuan District Police

Construction progress updated in August 2021 – Project of Renovation and expansion of main gate, build of reception house combined with installing equipment to manage national database on population of Tho Xuan District Police

The project of Renovation and expansion of the main gate, build of a reception house combined with installing equipment to manage the national database on population of Tho Xuan district police was commenced on July 4, 2021 at Area 6, Tho Xuan town, Tho Xuan district, Thanh Hoa province. It is expected that the project will be built in 90 days including Reception house, rebuilding of the main gate and southern fence, construction of a side gate and fence of the reception area, rebuilding of a parking house for guests, construction of an internal yard and equipment installation.
Construction progress updated in August 2021 – Typical Residential Area Infrastructure Project in Hoang Hoc Village, Dong Hoang Commune, Dong Son District, Thanh Hoa Province

Construction progress updated in August 2021 – Typical Residential Area Infrastructure Project in Hoang Hoc Village, Dong Hoang Commune, Dong Son District, Thanh Hoa Province

The Typical residential area infrastructure project in Hoang Hoc Village, Dong Hoang Commune, Dong Son District, Thanh Hoa Province was started on July 24, 2021 with an area of over 10 hectares, including main items: infrastructure construction of medium-voltage and low-voltage power lines, road system, surface water and wastewater drainage system and tree planting in the residential area. The Typical residential area infrastructure project has a total investment capital of over VND 68 billion, built in 341 days, meeting the needs of urban development, residential land needs of the people and contributing to the management and implementation of investment according to planning.