Construction progress updated in August 2021 – Dong Nam Residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province

Construction progress updated in August 2021 – Dong Nam Residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province

In August 2021, INVESTCORP Land Thanh Hoa has completed pulling and laying medium voltage underground cables, low voltage underground cables and installing substations; completed construction of rainwater drainage, wastewater drainage, grade 1 crushed stone of all roads and 40% of pavement tiles of Dong Nam residential area infrastructure project.
Construction progress updated in August 2021 – Star Villas project

Construction progress updated in August 2021 – Star Villas project

At the end of August 2021, INVESTCORP Myanmar continues to focus on completing villas No. 7, 8, 9 & 11 which are expected to hand over to the Investor in September and early October 2021. Currently, INVESTCORP Myanmar starts to carry out painting, gypsum ceiling, gate yard and finishing work for villas No. 3, 6, 10, 12 & 14. Villas No. 15 and 16 are continuing to be plastered and villa No. 1B is under construction of roof concrete structure and preparing to erect roof structure.
Construction progress updated in August 2021 – Lakeside Service Apartment (Myanmar) project

Construction progress updated in August 2021 – Lakeside Service Apartment (Myanmar) project

In August 2021, INVESTCORP Myanmar has completed the construction of all ground concrete, pile extraction and 50% of the dismantling of the formwork for ground beam and slab. The waterproofing of the exterior basement walls and sanding the exterior basement walls have also been completed. Other jobs have also been carried out in parallel such as repairing concrete surfaces and cleaning after dismantling formwork.
Update construction progress in July 2021– Manufacturing eco-friendly decor product project

Update construction progress in July 2021– Manufacturing eco-friendly decor product project

At the end of July 2021, in the office area of the Manufacturing eco-friendly decor product project, INVESTCORP 15 completed the construction of all concrete work for foundation, walls, fire tank covers and pump room.
Update construction progress in July 2021 – Dong Nam Residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province

Update construction progress in July 2021 – Dong Nam Residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province

In July 2021, INVESTCORP Land Thanh Hoa continued to construct and complete the remaining items of the Dong Nam Residential area infrastructure project, including construction of pulling and laying medium-voltage underground cables, building  sidewalk curbs; leveling, compaction of pavement soil, sand filling and paving sidewalk bricks according to design.
Update construction progress in July 2021 – Multifunctional house of Tho Xuan High school No 4, Tho Xuan district

Update construction progress in July 2021 – Multifunctional house of Tho Xuan High school No 4, Tho Xuan district

At the end of July 2021, INVESTCORP Land Thanh Hoa completed all remaining work items of the Multifunctional house of Tho Xuan High school No 4, Tho Xuan district including completion of construction and installation of corrugated iron roof and installation of indoor lighting equipment, construction of wooden floors and installation of door systems.
Update construction progress – Manufacturing eco-friendly decor product project in June 2021

Update construction progress – Manufacturing eco-friendly decor product project in June 2021

At the end of June 2021, INVESTCORP 15 has completed the entire construction of mass piling work for the factory and office area of the Manufacturing eco-friendly decor product project; completed 95% of concrete foundation and bracing of the factory foundation, 30% of the cold tank concrete cover, concrete of the ditch’s bottom and walls. The excavation of the basement and the fire tank has also been completed.
Update construction progress in June 2021 – Dong Nam Residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province

Update construction progress in June 2021 – Dong Nam Residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province

In June 2021, at the Dong Nam Residential area infrastructure project, INVESTCORP Land Thanh Hoa completed 80% of the road foundation and underground low-voltage electricity lines; completed the entire installation of light poles, 60% of pavements, 95% of green trees and 90% of clean water supply items.
Update construction progress – Lakeside Service Apartment (Myanmar) project in June 2021

Update construction progress – Lakeside Service Apartment (Myanmar) project in June 2021

At the end of June 2021, INVESTCORP Myanmar has completed dismantling the pile support system, completed 100% of the reinforced concrete volume of the basement walls and 30% of the reinforced concrete structure of the floor beams. Currently, the pile extraction, waterproofing and sanding of the basement walls are starting to be implemented.
Update construction progress – Star Villas project in June 2021

Update construction progress – Star Villas project in June 2021

At the end of June 2021, INVESTCORP Myanmar completed the concrete frame structure of Villas No. 10, 15 & 16; continue to implement the construction of Villa 1B’s structure and complete erecting the roof frame of Villa No. 10. Plastering work of Villas No. 3, 6, 7, 8, 9, 10, 11, 12 & 14 is also being speeded up in parallel with the painting and gypsum ceilings and walls of Villas No. 7, 8, 9 & 11.
Update construction progress – Multifunctional house of Tho Xuan High school No 4, Tho Xuan district in May 2021

Update construction progress – Multifunctional house of Tho Xuan High school No 4, Tho Xuan district in May 2021

At the end of May 2021, the Multifunctional house of Tho Xuan High school No 4 was completed by INVESTCORP Land Thanh Hoa finishing works of the inside and outside of the Multifunctional house; completed installation of electrical equipment, sanitary equipment; completed exterior painting work and erected truss structure and roof steel bracing.
Update construction progress – Manufacturing eco-friendly decor product project in May 2021

Update construction progress – Manufacturing eco-friendly decor product project in May 2021

In May 2021, INVESTCORP 15 Joint Stock Company completed all temporary works for the construction of the Manufacturing eco-friendly decor product project such as office buildings, temporary roads, electrical and water works, etc.
Update construction progress in May 2021 – Dong Nam Residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province

Update construction progress in May 2021 – Dong Nam Residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province

In May 2021, INVESTCORP Land Thanh Hoa continued executing the work items in the contract. The volume of work done in the month includes: Completing pulling 60% of the underground cables and erecting lighting poles; 90% of the planting of trees on the roads; completing casting, constructing and installing curbs for roads No. 4, 5, 6, 7, 10, 11 & 12; completing construction of grade 2 crushed stone foundation for road No. 10, grade 1 crushed stone foundation for roads No. 4, 5, 6, 7, 11 & 12.
Update construction progress – Lakeside Service Apartment (Myanmar) project in May 2021

Update construction progress – Lakeside Service Apartment (Myanmar) project in May 2021

After the temporary suspension of construction according to the direction of the Investor to ensure the safety of employees, the Lakeside Service Apartment (Myanmar) project has begun to construct again from April 27, 2021.
Update construction progress – Star Villas project in May 2021

Update construction progress – Star Villas project in May 2021

In May 2021, INVESTCORP Myanmar focused on building and completing the roof structure of Villas 6, 7, 8, 9, 11; speeding the construction of concrete frame structure of Villa No. 10, 15, 16 and foundation structure of Villa No. 1A, 1B.