Update construction progress – Multifunctional house of Tho Xuan High school No 4, Tho Xuan district in April 2021

Update construction progress – Multifunctional house of Tho Xuan High school No 4, Tho Xuan district in April 2021

In April 2021, at the Multifunctional house project of Tho Xuan 4 High School, INVESTCORP Land Thanh Hoa continued to execute the superstructure of the Multifunctional house. The works completed in the month include: 95% of the internal and external plastering works; completing tiling toilets, painting the exterior walls of the house, constructing wastewater drainage ditches and three-step stairs.
Update construction progress in April 2021 – Dong Nam Residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province

Update construction progress in April 2021 – Dong Nam Residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province

In April 2021, all items of the Dong Nam Residential area infrastructure project continued to be constructed and completed by INVESTCORP Land Thanh Hoa, including wastewater drainage systems for the roads No. 4, 5, 6 & 9; a part of the roads No. 10, 11 & 12; completed the installation of HDPE pipe for low voltage power supply from the road No. 1 to the road No. 7 and installed clean water supply system on the roads No. 5, 6 & 7. The construction of medium voltage transmission lines in the air, grade 2 gravel scattering on the roads No. 6, 7 and planting of trees around the detension basin have also been completed.
Update construction progress – Suga International (Vietnam) Factory project in April 2021

Update construction progress – Suga International (Vietnam) Factory project in April 2021

At the end of April 2021, INVESTCORP completed all items of the Suga International (Vietnam) Factory project to prepare to hand over to the Investor in early May 2021. After 8 months of construction, the project was completed on schedule meeting safety and quality requirements.
Groundbreaking ceremony of project of Manufacturing eco-friendly decor products

Groundbreaking ceremony of project of Manufacturing eco-friendly decor products

On the morning of April 22, 2021, the Groundbreaking ceremony of the project of Manufacturing eco-friendly decor products of INTCO Industry Vietnam Co., Ltd. was solemnly held at Bim Son Industrial Park, Bac Son ward, Bim Son town, Thanh Hoa province. Attending the ceremony were representatives of the Authority of the Nghi Son Economic Zone and Industrial Zones of Thanh Hoa province, representatives of Thanh Hoa Customs Department, representatives of Bim Son Town People's Committee, representatives of Investor, Construction contractors and distinguished guests.
Handover of New warehouse project – Peony factory

Handover of New warehouse project – Peony factory

On March 29, 2021, INVESTCORP completed and handed over the New warehouse project to the Investor – Maple Company Limited – Peony Branch.
Update construction progress – Multifunctional house of Tho Xuan High school No 4, Tho Xuan district in March 2021

Update construction progress – Multifunctional house of Tho Xuan High school No 4, Tho Xuan district in March 2021

At the end of March 2021, INVESTCORP Land Thanh Hoa completed 80% of the internal and external plastering work, completed ground concrete of the Multifunctional house project of Tho Xuan High school No. 4 and fabricated roof structural steel frame at the factory.
Update construction progress in March 2021 – Dong Nam Residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province

Update construction progress in March 2021 – Dong Nam Residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province

In March 2021, INVESTCORP Land Thanh Hoa continued the construction of concrete structures for drainage systems, installation of storm water drainage, construction of manholes, wastewater ditches and mobilization of macadam into the site. The works done in the month include the completion of the rainwater drainage system for roads No. 4, 5, 10, 11 and a part of road No. 12; completion of the wastewater drainage system for road No. 7 and the construction of road No. 6.
Update construction progress – Suga International (Vietnam) Factory project in March 2021

Update construction progress – Suga International (Vietnam) Factory project in March 2021

In March 2021, at the Main factory and the Office building of the Suga International  (Vietnam) factory project, INVESTCORP has completed the installation of panel walls inside and outside the factory area; completed the entire plastering work, 90% of the painting, gypsum ceiling, and 80% of the tiling. At present, INVESTCORP is continuing to construct internal finishing items such as ground epoxy, elevator installation, construction of aluminum and glass doors, iron doors, rolling doors and fire protection system.
Handover of Textile dyeing and garment factory project – Ramatex Nam Dinh phase 2

Handover of Textile dyeing and garment factory project – Ramatex Nam Dinh phase 2

In March 2021, INVESTCORP has completed the entire Textile dyeing and garment factory project – Ramatex Nam Dinh phase 2 and hand over to the Investor to put into use with a total floor area of 75,000sqm including a main factory, an office building, a canteen and auxiliary works.
Update construction progress of New warehouse project – Peony factory in February 2021

Update construction progress of New warehouse project – Peony factory in February 2021

In February 2021, INVESTCORP has completed the construction of concrete foundation, completed the construction of the roads and the outdoor rainwater drainage system at the New warehouse project - Peony Factory.
Update construction progress – Multifunctional house of Tho Xuan High school No 4, Tho Xuan district in February 2021

Update construction progress – Multifunctional house of Tho Xuan High school No 4, Tho Xuan district in February 2021

At the end of February 2021, INVESTCORP Land Thanh Hoa continued to construct the brickwork of the multifunctional house’s structure. The volume of the works done in the month includes fabrication and erection of formwork, reinforcement, concreting of curved roof beams cos + 9.80m and fabrication of steel structure at the factory.
Update construction progress in February 2021 – Dong Nam Residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province

Update construction progress in February 2021 – Dong Nam Residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province

In February 2021, INVESTCORP Land Thanh Hoa carried out the construction of concrete structures for drainage systems; construction and installation of sewers, building manholes to collect surface water and gathering macadam to the site.
Update construction progress – Suga International (Vietnam) Factory project in February 2021

Update construction progress – Suga International (Vietnam) Factory project in February 2021

At the end of February 2021, INVESTCORP has completed the corrugated iron roof of the factory, completed the erection of the exterior panel walls and 90% of the plastering of the Factory and Office of Suga International Factory (Vietnam) project. At present, INVESTCORP is continuing to construct indoor finishing items such as gypsum ceilings and walls, panel ceilings and walls, foundation paint, paintwork and fire protection system.
Update construction progress – Lakeside Service Apartment (Myanmar) project, Star Villas project and Norman Myanmar factory project in January 2021

Update construction progress – Lakeside Service Apartment (Myanmar) project, Star Villas project and Norman Myanmar factory project in January 2021

Due to the influence of the military coup on February 1, 2021, all projects in Myanmar including Lakeside Service Apartment (Myanmar) project, Star Villas project and Norman Myanmar factory project had to be suspended to ensure safety for all employees of INVESTCORP Myanmar and subcontractors working in the projects.