Update construction progress – Technical Infrastructure Project of Dong Nam New Residential Area, Dong Khe Commune, Dong Son District, Thanh Hoa Province in October 2020

Update construction progress – Technical Infrastructure Project of Dong Nam New Residential Area, Dong Khe Commune, Dong Son District, Thanh Hoa Province in October 2020

In October 2020, the Dong Nam Residential area infrastructure project was postponed due to rainy weather affecting the excavation and infrastructure construction.
Update construction progress – Lakeside Service Apartment (Myanmar) project in October 2020

Update construction progress – Lakeside Service Apartment (Myanmar) project in October 2020

In October 2020, the Lakeside Service Apartment (Myanmar) project continued to be postponed all construction works under the direction of the Yangon city government due to the second outbreak of the COVID-19 pandemic. According to the newly received information, with the full preparation of disease prevention measures as required, the city government will agree to allow the project to continue construction in early November 2020.
Update construction progress – Suga International (Vietnam) Factory project in October 2020

Update construction progress – Suga International (Vietnam) Factory project in October 2020

At the end of October 2020, INVESTCORP has completed all temporary works at Suga International (Vietnam) Factory project.
Update construction progress – Star Villas project in October 2020

Update construction progress – Star Villas project in October 2020

On October 21, 2020, after a month being postponed due to the resurgence and complicated developments of the Covid-19 pandemic, the city government allowed the Star Villas project to be reopened.
Update construction progress – Phase 4 factory construction project of Yokowo Vietnam Co., Ltd in October 2020

Update construction progress – Phase 4 factory construction project of Yokowo Vietnam Co., Ltd in October 2020

At the end of October 2020, at the Main factory of the Phase 4 factory construction project of Yokowo Vietnam Co., Ltd, INVESTCORP completed construction of gypsum walls and ceilings, sandwich walls and ceilings, toilet partitions and internal and external painting work. It is expected that all Main factory area will be cleaned, accepted and handed over in early November 2020.
Update construction progress of Textile dyeing and garment factory project – Ramatex Nam Dinh phase 2 in October 2020

Update construction progress of Textile dyeing and garment factory project – Ramatex Nam Dinh phase 2 in October 2020

In October 2020, at the Main factory area of the Textile dyeing and garment factory project – Ramatex Nam Dinh phase 2, INVESTCORP completed the entire main structure, staircase structure and internal and external plastering work in Zone 1, Zone 2. Other finishing works are being carried out in parallel. It is expected that all plaster work will be completed in November 2020.
Update construction progress – Crystal Martin Vietnam factory project in October 2020

Update construction progress – Crystal Martin Vietnam factory project in October 2020

In October 2020, the renovation of the 6th floor of R1C building into an office - Crystal Martin Vietnam factory project continued to be constructed by INVESTCORP according to schedule.
Update construction progress – Star Villas project in September 2020

Update construction progress – Star Villas project in September 2020

Star Villas project, invested by Thanlyin Estate Development Ltd. under Yoma Group in Star City urban area - Thanlyin - Yangon – Myanmar, was commenced by INVESTCORP Myanmar in early September 2020.
Update construction progress – Phase 4 factory construction project of Yokowo Vietnam Co., Ltd in September 2020

Update construction progress – Phase 4 factory construction project of Yokowo Vietnam Co., Ltd in September 2020

In September 2020, INVESTCORP completed 80% of the volume of ceilings and gypsum walls, 100% of sandwich walls and ceilings and the entire exterior window system in the expansion area of the Main factory of the Phase 4 factory construction project of Yokowo Vietnam Co., Ltd. Currently, painting and skimcoat works are being carried out in compliance with the construction progress.
Update construction progress of Textile dyeing and garment factory project – Ramatex Nam Dinh phase 2 in September 2020

Update construction progress of Textile dyeing and garment factory project – Ramatex Nam Dinh phase 2 in September 2020

At the end of September 2020, INVESTCORP has completed the construction of all concrete structures in Zone 1, Zone 2 and the 4th floor of Zone 3 in the Main factory; completed construction of walls and plastering in Zone 1 and Zone 2. It is expected that in October 2020, INVESTCORP will continue to build walls in Zone 3 and build inside and outside the entire factory.
Update construction progress – Lakeside Service Apartment (Myanmar) project in September 2020

Update construction progress – Lakeside Service Apartment (Myanmar) project in September 2020

In September 2020, INVESTCORP Myanmar completed the piling work and is now focusing on excavation in combination with the installation of the remaining piling support system. The construction of reinforced concrete structures in the basement started to be executed including lean concrete pouring, reinforcing fabrication and installation of formwork of foundation framework.
Update construction progress – Technical Infrastructure Project of Dong Nam New Residential Area, Dong Khe Commune, Dong Son District, Thanh Hoa Province in September 2020

Update construction progress – Technical Infrastructure Project of Dong Nam New Residential Area, Dong Khe Commune, Dong Son District, Thanh Hoa Province in September 2020

Dong Nam residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province, invested by the Management Board of construction and investment projects of Dong Son district having an area of nearly 10ha. Dong Nam residential area infrastructure project was commenced on July 3, 2020 by INVESTCORP Land Thanh Hoa Company Limited including traffic roads, water supply and drainage system, power supply system, green infrastructure and balancing reservoir.
Update construction progress – Crystal Martin Vietnam factory project in September 2020

Update construction progress – Crystal Martin Vietnam factory project in September 2020

In September 2020, INVESTCORP continued to execute the renovation of the 6th floor of R1C building into an office at the Crystal Martin Vietnam factory project.
2nd anniversary of establishment of INVESTCORP Land Thanh Hoa Company Limited

2nd anniversary of establishment of INVESTCORP Land Thanh Hoa Company Limited

On September 19, 2020, the 2nd anniversary of INVESTCORP Land Thanh Hoa Company Limited was held at the Company's headquarters No. 166 Trieu Quoc Dat, Dien Bien Ward, Thanh Hoa City. Attending the ceremony was the presence of the Board of Directors and all staff of the Company.
Groundbreaking ceremony of Suga International (Vietnam) Factory Projects

Groundbreaking ceremony of Suga International (Vietnam) Factory Projects

On the morning of September 18, 2020, the Groundbreaking ceremony of Suga International (Vietnam) Factory Project was held at lot CN11-3, Que Vo 3 Industrial Park, Que Tan commune, Que Vo district, Bac Ninh province. The ceremony was fully attended by representatives of Investor - Suga International (Vietnam) Company Limited, representatives of Management Board of Que Vo 3 Industrial Park and representatives of Construction Contractor - INVESTCORP Company.