Update construction progress of Textile dyeing and garment factory project – Ramatex Nam Dinh phase 2 in February 2021

Update construction progress of Textile dyeing and garment factory project – Ramatex Nam Dinh phase 2 in February 2021

In February 2021, INVESTCORP completed all the indoor work items to carry out inspection and handover of each part to the Investor.
Update construction progress of New warehouse project – Peony factory in January 2021

Update construction progress of New warehouse project – Peony factory in January 2021

The new warehouse project - Peony factory was commenced on December 1, 2020 with an area of 1760 m2 in the form of steel-frame house, corrugated iron walls combined with 1m high walls and concrete ground.
Update construction progress of Norman Myanmar factory project in January 2021

Update construction progress of Norman Myanmar factory project in January 2021

The Norman Myanmar factory project was started on January 10, 2021 by INVESTCORP Myanmar in Zone B - Thilawa Special economic zone.
Update construction progress – Multifunctional house of Tho Xuan High school No 4, Tho Xuan district in January 2021

Update construction progress – Multifunctional house of Tho Xuan High school No 4, Tho Xuan district in January 2021

In January 2021, INVESTCORP Land Thanh Hoa focused on the construction of the Multi-functional house’s structure. The works that have been done in the month include the concrete work of the slab and beam on the 2nd floor cos + 4.8m, construction of formwork and reinforcement, pouring concrete on the 2nd floor, completion of building brick walls on the 2nd floor to cos + 9.8m and the fabrication of steel frame roof at the factory.
Update construction progress in January 2021 – Dong Nam Residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province

Update construction progress in January 2021 – Dong Nam Residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province

At the end of January 2021, INVESTCORP Land Thanh Hoa continued constructing and completing the compaction of K95 soil on the sidewalk, casting drainage structures and gathering macadam to the site. At present, INVESTCORP Land Thanh Hoa is constructing and installing drainage culverts on the roads.
Update construction progress – Lakeside Service Apartment (Myanmar) project in January 2021

Update construction progress – Lakeside Service Apartment (Myanmar) project in January 2021

In January 2021, INVESTCORP Myanmar has completed all reinforced concrete structures of the basement ground and slab and continues implementing other works at the basement such as pouring wall reinforced concrete, waterproofing of the walls’ external surface, sand filling and disassembly of pile support system.
Update construction progress – Suga International (Vietnam) Factory project in January 2021

Update construction progress – Suga International (Vietnam) Factory project in January 2021

At the end of January 2021, at the Factory and Office area of Suga International (Vietnam) factory project, INVESTCORP completed all the erection of steel structures and painting of concrete ceiling on the second floor, completing 90% of the wall construction, 80% of the internal plastering and 20% of the tiling. Exterior panel frame system has been completed and is about to move to construct paneling, gypsum ceiling and floor painting.
Update construction progress – Star Villas project in January 2021

Update construction progress – Star Villas project in January 2021

In January 2021, INVESTCORP Myanmar completed and handed over the Villa No. 5 to the Investor for use on January 20, 2021 according to the expected schedule.
Update construction progress of Textile dyeing and garment factory project – Ramatex Nam Dinh phase 2 in January 2021

Update construction progress of Textile dyeing and garment factory project – Ramatex Nam Dinh phase 2 in January 2021

At the end of January 2021, the entire warehouse item at Textile dyeing and garment factory project – Ramatex Nam Dinh phase 2 was completed and handed over to the Investor to put into use.
Update construction progress – Crystal Martin Vietnam factory project in January 2021

Update construction progress – Crystal Martin Vietnam factory project in January 2021

On January 28, 2021, the Renovation of the 6th floor of R1C building into an office - Crystal Martin Vietnam Factory Project was handed over to the Investor and put into use by INVESTCORP after being accepted on January 20 & 21, 2021.
Update construction progress – Multifunctional house of Tho Xuan High school No 4, Tho Xuan district in November 2020

Update construction progress – Multifunctional house of Tho Xuan High school No 4, Tho Xuan district in November 2020

In December 2020, the multifunctional house project of Tho Xuan High school No. 4, Tho Xuan District continued to be focused on speeding up construction by INVESTCORP Land Thanh Hoa. Currently, the construction of formwork and reinforcement, concreting the first floor columns, building the first floor walls and the 3-step stair in front of the house have been completed.
Update construction progress in December 2020 – Dong Nam Residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province

Update construction progress in December 2020 – Dong Nam Residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province

In December 2020, INVESTCORP Land Thanh Hoa continued to focus on the construction of road’s surface structures such as the treatment of weak roadbeds due to being flooded during storms, the excavation of organic soil of roads No. 4, 5, 10, 11 and 13. The K95 and K98 backfilling work for the roads has reached 90% of the workload.
Update construction progress – Lakeside Service Apartment (Myanmar) project in December 2020

Update construction progress – Lakeside Service Apartment (Myanmar) project in December 2020

In December 2020, INVESTCORP Myanmar completed all the excavation of the foundation framework and are now carrying out the construction of the work items at the basement. Reinforced concrete structures are also being implemented such as reinforced concrete for basement foundation framework and bottom slab combined with foundation framework. The water tank walls under the basement floor has been completed 100% of the volume. The processing and erection of formwork, reinforcement of the basement’s ground and the water tank’s slab are continuing to accelerate construction.
Update construction progress – Suga International (Vietnam) Factory project in December 2020

Update construction progress – Suga International (Vietnam) Factory project in December 2020

At the end of December 2020, all concrete floor for the Factory and Office at the Suga International (Vietnam) Factory project was completed. In the Factory area, INVESTCORP has completed 20% of the ground floor work of the first floor, started the construction of steel structures on the second floor and implemented the construction and painting of ceiling concrete.