Company news

Construction progress updated in March 2023 - Vina Ito Factory Project Phase 2

Construction progress updated in March 2023 - Vina Ito Factory Project Phase 2

In March 2023, INVESTCORP 15 completed pouring concrete of the factory floor; along with that, tiling the toilet area of the factory, installing curbs, completing manholes, and completing garbage houses were also completed.
Construction progress updated in March 2023 - TOYO INK COMPOUNDS Vietnam Factory Project Phase 3

Construction progress updated in March 2023 - TOYO INK COMPOUNDS Vietnam Factory Project Phase 3

At the end of March 2023, INVESTCORP 10 has completed the pile pressing works for the main factory, warehouse and powerhouse.
Groundbreaking Ceremony of Urban Renovation Project in Sao Vang town, Tho Xuan district; Item: Lighting system for Nguyen Mau Tuyen, Trinh Khac Phuc, Tran Hoanh streets and road from Xuan Long to Xuan Hop

Groundbreaking Ceremony of Urban Renovation Project in Sao Vang town, Tho Xuan district; Item: Lighting system for Nguyen Mau Tuyen, Trinh Khac Phuc, Tran Hoanh streets and road from Xuan Long to Xuan Hop

On the afternoon of February 28, 2023, Tho Xuan district held the groundbreaking ceremony of the Urban Renovation Project in Sao Vang town, Tho Xuan district; Item: Lighting system for Nguyen Mau Tuyen, Trinh Khac Phuc, Tran Hoanh streets and road from Xuan Long to Xuan Hop. The project is invested by the People's Committee of Sao Vang town for the purpose of public lighting to ensure security and social order, as well as the lives of people in the area.
Construction progress updated in March 2023 – Dai Lai Eco-Residence and Resort Project, Ngoc Thanh Commune, Phuc Yen City, Vinh Phuc Province

Construction progress updated in March 2023 – Dai Lai Eco-Residence and Resort Project, Ngoc Thanh Commune, Phuc Yen City, Vinh Phuc Province

By the end of March 2023, INVESTCORP CREATION has completed the work items under the "Construction of earth retaining wall" package. During the month, the Company has completed 100% of the erection works of reinforcement, formwork and concrete pouring of retaining walls, construction of backfilling.
Construction progress updated in March 2023 – Road project from Xuan Hung commune connecting with road from Tho Xuan town to Lam Son – Sao Vang urban area, Tho Xuan district

Construction progress updated in March 2023 – Road project from Xuan Hung commune connecting with road from Tho Xuan town to Lam Son – Sao Vang urban area, Tho Xuan district

In March 2023, INVESTCORP Land Thanh Hoa completed the construction of crushed stone and asphalted the road surface, and completed the installation of the drainage system. Total output is estimated at 67% of the contract volume.
Construction progress updated in March 2023 - Project of renovating and upgrading rescue road in Truong Xuan commune to left dike of Chu river, Tho Xuan district, Thanh Hoa province

Construction progress updated in March 2023 - Project of renovating and upgrading rescue road in Truong Xuan commune to left dike of Chu river, Tho Xuan district, Thanh Hoa province

In March 2023, the construction of soil excavation, crushed stone, concrete formwork, K98 compaction, and concrete pouring to return the drainage ditch were 100% completed by INVESTCORP Land Thanh Hoa. At the same time, the work of digging and spreading underground cables to install electrical equipment, the construction of macadam and road asphalt have also been completed. Total construction output is estimated at 49% of the contract volume.
Construction progress updated in March 2023 – Sao Mai Resort Project, Tho Lam Commune – Tho Xuan District – Thanh Hoa Province

Construction progress updated in March 2023 – Sao Mai Resort Project, Tho Lam Commune – Tho Xuan District – Thanh Hoa Province

In March 2023, INVESTCORP 6 continued to construct items, including reception house, Rubby Four Seasons villa area, Bungalow under the lake and other ancillary items.
Construction progress updated in March 2023 – Sakata Inx Vietnam Factory Project - Bac Ninh Branch

Construction progress updated in March 2023 – Sakata Inx Vietnam Factory Project - Bac Ninh Branch

In March 2023, INVESTCORP 15 completed auxiliary works including internal asphalt spreading and surrounding grass planting. In parallel, both main factory package and auxiliary factory package are also cleaned and repaired outstanding defects by INVESTCORP 15.
Construction progress updated in March 2023 – Sao Mai Lam Son - Sao Vang New Urban Area Project, Xuan Thang Commune, Tho Xuan District, Thanh Hoa Province

Construction progress updated in March 2023 – Sao Mai Lam Son - Sao Vang New Urban Area Project, Xuan Thang Commune, Tho Xuan District, Thanh Hoa Province

In March 2023, INVESTCORP 6 continued to construct the items under the contract including leveling the ground, pouring concrete, installing curb stones, paving pavements, completing manholes and around flower beds. Accumulated construction volume by the end of March 2023 reached 35%.
Construction progress updated in March 2023 - Renovation and upgrading project of provincial road 506B, section from Tho Lap commune to Xuan Tin commune, Tho Xuan district

Construction progress updated in March 2023 - Renovation and upgrading project of provincial road 506B, section from Tho Lap commune to Xuan Tin commune, Tho Xuan district

At the beginning of March 2023, INVESTCORP Land Thanh Hoa gathered machinery and human resources to carry out the construction of work items according to the signed contract.
A Talk to celebrate International Women's Day 8/3

A Talk to celebrate International Women's Day 8/3

Joining the joyful atmosphere to celebrate International Women's Day, on the morning of March 8, 2023, INVESTCORP Group held a talk at its headquarters. Attending the talk was the Group's Board of Directors, heads of departments and especially all female staff working at the Group's Office.
Construction progress updated in February 2023 - TOYO INK COMPOUNDS Vietnam Factory Project Phase 3

Construction progress updated in February 2023 - TOYO INK COMPOUNDS Vietnam Factory Project Phase 3

By the end of February 2023, INVESTCORP 10 has completed the temporary erection works for construction and completed 100% of the pile pressing and compression test for the main factory and warehouse.
Construction progress updated in February 2023 - Vina Ito Factory Project Phase 2

Construction progress updated in February 2023 - Vina Ito Factory Project Phase 2

In February 2023, INVESTCORP 15 has completed building and plastering the factory walls, constructing layer 1 of the internal road and rainwater drainage system. Along with that, the construction of the garbage house walls and the installation of V steels for manhole covers are also being implemented by INVESTCORP 15.
Construction progress updated in February 2023 – Sakata Inx Vietnam Factory Project - Bac Ninh Branch

Construction progress updated in February 2023 – Sakata Inx Vietnam Factory Project - Bac Ninh Branch

In February 2023, for the main factory package, the remaining works such as tiling, mechanics and foundations for machines of all kinds have been completed by INVESTCORP 15. For the exterior package, INVESTCORP 15 has also completed the handover of ancillary items, is implementing internal roads and installing sidewalk curbs.