Company news

Construction progress updated in November 2021 – Typical Residential Area Infrastructure Project in Hoang Hoc Village, Dong Hoang Commune, Dong Son District, Thanh Hoa Province

Construction progress updated in November 2021 – Typical Residential Area Infrastructure Project in Hoang Hoc Village, Dong Hoang Commune, Dong Son District, Thanh Hoa Province

At the end of November 2021, INVESTCORP Land Thanh Hoa continues to implement the work items of the Typical Residential Area Infrastructure Project in Hoang Hoc Village, Dong Hoang Commune, Dong Son District, Thanh Hoa Province and has completed to 90% of the K95 soil, 70% of K98 soil and 70% of low voltage electric poles. In addition, the construction of surface water drainage system and the construction of crushed stone type 2 are also being implemented in parallel.
Construction progress updated in November 2021 – Dong Nam Residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province

Construction progress updated in November 2021 – Dong Nam Residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province

In November 2021, Dong Nam Residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province continued to be executed laying underground electrical cables, tiling sidewalk and demolishing temporary road to return the site to the Investor by INVESTCORP Land Thanh Hoa Company Limited.
Construction progress updated in November 2021 – Star Villas project

Construction progress updated in November 2021 – Star Villas project

In November 2021, the situation in Myanmar continued to be complicated with protests and riots taking place more often, however, INVESTCORP Myanmar still tried to continue the construction and completion of the Star Villas project as per the primary objective.
Construction progress updated in October 2021 – Design and build project of Welco Technology Vietnam Factory

Construction progress updated in October 2021 – Design and build project of Welco Technology Vietnam Factory

In October 2021, at the Design and build project of Welco Technology Vietnam Factory, INVESTCORP 9 has started to implement pile pressing, excavation of main factory foundation and auxiliary items after completing the temporary works. Currently, the pile pressing has been completed up to 70% of the work volume.
Construction progress updated in October 2021 – Project of Repairing damage of roadbed, road surface and drainage system section Km3+00 -:- Km10+500, National way 47B, Thanh Hoa province

Construction progress updated in October 2021 – Project of Repairing damage of roadbed, road surface and drainage system section Km3+00 -:- Km10+500, National way 47B, Thanh Hoa province

In October 2021, the project of Repairing damage of roadbed, road surface and drainage system section Km3+00 -:- Km10+500, National way 47B, Thanh Hoa province has been implemented and completed by INVESTCORP Land Thanh Hoa 100% of asphalt concrete, 95% of the drainage system and is currently carried out casting safety poles.
Construction progress updated in October 2021 – Toray International Vietnam factory project in Quang Ngai

Construction progress updated in October 2021 – Toray International Vietnam factory project in Quang Ngai

In October 2021, INVESTCORP 9 has completed wet work of the office, factory and canteen of the Toray International Vietnam Factory project in Quang Ngai and moved to finishing works.
Construction progress updated in October 2021– Manufacturing eco-friendly decor product project

Construction progress updated in October 2021– Manufacturing eco-friendly decor product project

In October 2021, the Manufacturing eco-friendly decor product project has been completed the construction of concrete lining of the factory ground, the concrete roof of power room, the concrete walls of chemical house and walls on the 2nd floor of the office building. Currently, INVESTCORP 15 is implementing the construction of the 3rd floor walls of the office area and construction of 90% of the concrete works for the factory ground.
Construction progress updated in October 2021 – Yi Da Garment Factory Project Phase 3 - Canteen parking

Construction progress updated in October 2021 – Yi Da Garment Factory Project Phase 3 - Canteen parking

At the end of October 2021, INVESTCORP Dong Minh has completed all construction items of the Yi Da Garment Factory project Phase 3 - Canteen parking and carried out acceptance to handed over the project to the Investor to put into use.
Construction progress updated in October 2021 – Typical Residential Area Infrastructure Project in Hoang Hoc Village, Dong Hoang Commune, Dong Son District, Thanh Hoa Province

Construction progress updated in October 2021 – Typical Residential Area Infrastructure Project in Hoang Hoc Village, Dong Hoang Commune, Dong Son District, Thanh Hoa Province

In October 2021, INVESTCORP Land Thanh Hoa continues to implement the work items of the Typical Residential Area Infrastructure Project in Hoang Hoc Village, Dong Hoang Commune, Dong Son District, Thanh Hoa Province such as construction of drainage system, gathering and distribution of crushed stone to the construction site, casting prefabricated concrete components for the drainage system and electrical system etc.
Construction progress updated in October 2021 – Dong Nam Residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province

Construction progress updated in October 2021 – Dong Nam Residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province

At the end of October 2021, in the Dong Nam Residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province, INVESTCORP Land Thanh Hoa has completed the construction of asphalt concrete for 9000sqm of roads and 75% of sidewalk paving.
Construction progress updated in October 2021 – Star Villas project

Construction progress updated in October 2021 – Star Villas project

Due to the impact of the Covid-19 pandemic, INVESTCORP Myanmar could not concentrate much manpower to accelerate the project progress as expected.
Construction progress updated in October 2021– Lakeside Service Apartment (Myanmar) project

Construction progress updated in October 2021– Lakeside Service Apartment (Myanmar) project

On October 15, 2021, INVESTCORP Myanmar completed all items within the scope of works under the contract of Lakeside Service Apartment (Myanmar) project and handed it over to the Investor - Japan Inya Investment Company Limited.
Crystal Martin (Vietnam) Office Project constructed by INVESTCORP posted on many prestigious international architecture websites.

Crystal Martin (Vietnam) Office Project constructed by INVESTCORP posted on many prestigious international architecture websites.

With a unique design, the office project of Crystal Martin (Vietnam) Company Limited in Quang Chau industrial park, Viet Yen district, Bac Giang province constructed by INVESTCORP has been posted on many prestigious international architecture websites such as Archdaily, Archilovers.
Commencement of construction project to expand Thermostat factory for cars and motorcycles

Commencement of construction project to expand Thermostat factory for cars and motorcycles

In order to meet the needs of the market and improve the production conditions of the factory, Nippon Thermostat Vietnam Company Limited has invested in the construction project to expand the Thermostat factory for cars and motorcycles in Dong Van II Industrial Park, Duy Tien District, Ha Nam Province.
Construction progress updated in September 2021 – Design and build project of Welco Technology Vietnam Factory

Construction progress updated in September 2021 – Design and build project of Welco Technology Vietnam Factory

The Design and build project of Welco Technology Vietnam Company Limited factory was implemented by INVESTCORP 9 at Lot A19, An Phat High-Technology Industrial Park, Viet Hoa ward, Hai Duong city, Hai Duong province with a total area of over 17,000m2.