Construction progress updated in May 2022 - New Factory Construction Project of AIR WATER Vietnam Co., Ltd in Ha Nam

Construction progress updated in May 2022 - New Factory Construction Project of AIR WATER Vietnam Co., Ltd in Ha Nam

In May 2022, INVESTCORP 15 has implemented and completed the following items: concrete work of the factory floor and the machine foundation. In the office area, concrete beams surrounding the roof for the steel structure to be erected have been completed by INVESTCORP 15.
Construction progress updated in May 2022 - New An Nam Matsuoka Garment Factory project – Phase 3B

Construction progress updated in May 2022 - New An Nam Matsuoka Garment Factory project – Phase 3B

In the main building, INVESTCORP 9 has completed the entire construction of the reinforced concrete for the foundation framework and foundation brace. The works of erecting columns and building mezzanine walls to install roof steel structures and corrugated iron walls have reached 60% of the workload.
Construction progress updated in May 2022 – Technical infrastructure project of residential area in Quang Dong commune, Thanh Hoa city, Thanh Hoa province

Construction progress updated in May 2022 – Technical infrastructure project of residential area in Quang Dong commune, Thanh Hoa city, Thanh Hoa province

In May 2022, INVESTCORP Land Thanh Hoa Company Limited has carried out the works such as excavation, organic dredging of roadbeds reached 75%; K98 embankment construction of roads reached 50% of the contract volume. The roads that have been constructed include: road 1, road 2, road 3, road 5, road 6 which are processing concrete casting for pavement structures, installing and building manholes, drainage pits.
Construction progress update in May 2022 – Road project from Xuan Hung commune connecting with road from Tho Xuan town to Lam Son – Sao Vang urban area, Tho Xuan district

Construction progress update in May 2022 – Road project from Xuan Hung commune connecting with road from Tho Xuan town to Lam Son – Sao Vang urban area, Tho Xuan district

At the end of May 2022, INVESTCORP Land Thanh Hoa Company Limited has implemented the construction of items, including: excavation, dredging of organic soil; embankment of K95 road reached 95% and K98 reached 13% of the contract volume; the cutoff dike reached 70% of the volume, the foundation excavation, mold, and structure excavation have also been completed. Currently, INVESTCORP Land Thanh Hoa is carrying out concrete structure casting and starts to install sewers and trenches.
Construction progress updated in May 2022 – Manufacturing eco-friendly decor product project

Construction progress updated in May 2022 – Manufacturing eco-friendly decor product project

In May 2022, INVESTCORP 15 has completed the remaining items of the office area, including the construction of drywall ceilings, aluminum ceilings, aluminum glass walls, installation of panels, sound-absorbing panels, painting walls and installation of furniture, tables and chairs.
Construction progress update in May 2022 – Design and build project of Welco Technology Vietnam Factory

Construction progress update in May 2022 – Design and build project of Welco Technology Vietnam Factory

At the end of May 2022, in the main house area, INVESTCORP 9 has completed all the works. At present, the industrial cleaning and system inspection works are completed by INVESTCORP 9 and prepared for acceptance and handover to the Investor.
Construction progress update in May 2022 – Typical Residential Area Infrastructure Project in Hoang Hoc Village, Dong Hoang Commune, Dong Son District, Thanh Hoa Province

Construction progress update in May 2022 – Typical Residential Area Infrastructure Project in Hoang Hoc Village, Dong Hoang Commune, Dong Son District, Thanh Hoa Province

In May 2022, INVESTCORP Land Thanh Hoa Company Limited focused on implementing and executing the items in the contract, including the construction of the crushed stone base layer grade II reached 80% and the upper layer grade I reached 50%; installation of curbs reached 80%; sidewalk tiling reached 65%; planting reached 30%; the road surface drainage system reached 85% of the volume.
Construction progress update in May 2022 – Dong Nam Residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province

Construction progress update in May 2022 – Dong Nam Residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province

At the end of May 2022, INVESTCORP Land Thanh Hoa Company Limited has completed the items in the contract, including pavement tiling, repairing, compacting and finishing the road surface, installation of the frame and composite cover.
Construction progress update in May 2022 – Star Villas project

Construction progress update in May 2022 – Star Villas project

At the end of May 2022, INVESTCORP Myanmar has completed and handed over to put into use 13 out of 14 Villas.
INVESTCORP Land Thanh Hoa organizes Team building 2022

INVESTCORP Land Thanh Hoa organizes Team building 2022

Continuing the culture of INVESTCORP Group, from May 21 to 22, 2022, INVESTCORP Land Thanh Hoa Co., Ltd held a Team building program at Hai Hoa beach. This is an activity to help all employees have time to rest and relax as well as promoting the spirit of solidarity, creativity and tightening the collective spirit as the message of the program "Playing is a must".
INVESTCORP Group appoints Senior personnel – Project Development Director

INVESTCORP Group appoints Senior personnel – Project Development Director

To strengthen building and expanding relationships with partners and customers especially Japanese customers, on May 4, 2022 at the Group's Head office, INVESTCORP appointed Mr. Tomita Takahisa as Project Development Manager of the Group.
Construction progress update in April 2022 – Renovation project of lake, campus and walkway in Bac Luong commune, Tho Xuan district

Construction progress update in April 2022 – Renovation project of lake, campus and walkway in Bac Luong commune, Tho Xuan district

At the end of April 2022, INVESTCORP Land Thanh Hoa Company Limited has completed all the items of the Renovation project of lake, campus and walkway in Bac Luong commune, Tho Xuan district. The project has been constructed 45 days ahead of schedule and is completing the procedures to sign the minutes of acceptance, handover and put into use. The project was highly appreciated by the leaders of Tho Xuan district as well as the investor for the quality of the work, progress and design standards.
Construction progress update in April 2022 – Road project from Xuan Hung commune connecting with road from Tho Xuan town to Lam Son – Sao Vang urban area, Tho Xuan district

Construction progress update in April 2022 – Road project from Xuan Hung commune connecting with road from Tho Xuan town to Lam Son – Sao Vang urban area, Tho Xuan district

At the end of April 2022, INVESTCORP Land Thanh Hoa Company Limited has gathered machinery, materials and human resources to implement the construction of the road project from Xuan Hung commune connecting with road from Tho Xuan town to Lam Son – Sao Vang urban area, Tho Xuan district. The works implemented in the month including digging, dredging organic soil, digging foundation - mold – bench cut reached 65% of the workload; construction of embankment of road K95 achieved 55%, K98 achieved 7% of the contract value.
Construction progress update in April 2022– Manufacturing eco-friendly decor product project

Construction progress update in April 2022– Manufacturing eco-friendly decor product project

In April 2022, INVESTCORP 15 has completed the items of the factory. The office was urgently constructed and completed by INVESTCORP 15, reaching 85% of the workload, including drywall ceilings, aluminum and glass walls, ceiling and wall painting and interior installation. The drywall ceilings and walls are also being urgently constructed.
Construction progress update in April 2022 – Design and build project of Welco Technology Vietnam Factory

Construction progress update in April 2022 – Design and build project of Welco Technology Vietnam Factory

At the end of April 2022, in the main house, INVESTCORP 9 has completed the structural and plastering work. The ceiling and wall construction, wall painting, floor finishing, door and window installation, electromechanical equipment has reached 95% of the total workload.