Update construction progress of Tamada Office and Warehouse project in June 2019

Update construction progress of Tamada Office and Warehouse project in June 2019

At the end of June 2019, INVESTCORP Myanmar completed installing and fixing the wall iron. The installation and fixing of roof sheet and roof water trough are under construction and expect to be completed in mid-July 2019.
Update construction progress – Sankyo project in June 2019

Update construction progress – Sankyo project in June 2019

At the end of June 2019, INVESTCORP Myanmar received the office area from the Owner to implement finishing works and is expected to receive the workshop area in July 2019.
Update construction progress of Myanmar Meranti project’s Ruby in June 2019

Update construction progress of Myanmar Meranti project’s Ruby in June 2019

At present, the Myanmar Meranti project’s Ruby of JFE Meranti Myanmar Co., Ltd has been basically completed to partially inspected and handed over to the Owner for use.
Update construction progress – Golden Land Project Pharmaceutical Factory in June 2019

Update construction progress – Golden Land Project Pharmaceutical Factory in June 2019

In June 2019, the workshop was finished brickwork and some basic finishing works. The pump room and the guardhouse have also been implemented brickwork.
Official launching ceremony of Xuan Tien Investcorp residential area project

Official launching ceremony of Xuan Tien Investcorp residential area project

On June 1, 2019, the official launching ceremony of Xuan Tien Investcorp residential area project was held by INVESTCORP Land Thanh Hoa Company Ltd., - INVESTCORP's member company in coordination with the Distributor - Phuc Hung Corporation attracting a lot of customers from local district and neighboring districts.
Update construction progress of Textile dyeing and garment factory project– Ramatex Nam Dinh in May 2019

Update construction progress of Textile dyeing and garment factory project– Ramatex Nam Dinh in May 2019

In May 2019, at the textile area of the Textile dyeing and garment factory project - Ramatex Nam Dinh, INVESTCORP completed erection of the roof steel structures and is carrying out roof work and casting ground concrete. As expected, brickwork and plastering work of the toilet area, power room and compressing room will be implemented and completed in June 2019. Besides, the internal and external putty work of the textile factory’s walls are also implemented in parallel.
Update construction progress of Vietnam Mie factory project phase 2 in May 2019

Update construction progress of Vietnam Mie factory project phase 2 in May 2019

In May 2019, at the Vietnam Mie factory project phase 2, INVESTCORP implemented the painting work, tiling and gypsum ceilings and partitions. The aluminum doors and fire rated steel doors have been fabricated and erected the frames. The steel structures have also been implemented and completed.
Update construction progress of EMS extension project of Meiko Electronics Vietnam Company Ltd in May 2019

Update construction progress of EMS extension project of Meiko Electronics Vietnam Company Ltd in May 2019

In May 2019, INVESTCORP completed and handed over some additional items under scope of the EMS extension project of Meiko Electronics Vietnam Company Ltd.

Update construction progress of Tamada Office and Warehouse project in May 2019

At the end of May 2019, INVESTCORP Myanmar completed roof work of the office and workshop areas. The wall corrugated iron has been implemented and is expected to complete in June 2019.
Update construction progress – Sankyo project in May 2019

Update construction progress – Sankyo project in May 2019

At the end of May 2019, INVESTCORP Myanmar completed the foundation and ground at the office area of the Sankyo project and handed over to the Owner to implement following works.
Update construction progress of Myanmar Meranti project’s Ruby in May 2019

Update construction progress of Myanmar Meranti project’s Ruby in May 2019

In May 2019, INVESTCORP Myanmar continued to execute the painting and finishing works of the ancillary area. Other finishing works are also implemented in parallel.
Update construction progress – Golden Land Project Pharmaceutical Factory in May 2019

Update construction progress – Golden Land Project Pharmaceutical Factory in May 2019

In May 2019, INVESTCORP Myanmar continued implementing workshop and underground tank system. The PIT foundation system has been carried out 80% and will be completed in June 2019.
Groundbreaking ceremony of Nihon Plast Vietnam factory project

Groundbreaking ceremony of Nihon Plast Vietnam factory project

On May 22, 2019, INVESTCORP held a groundbreaking ceremony of the Nihon Plast Vietnam factory project in Thang Long industrial park (Vinh Phuc) - Thien Ke commune, Binh Xuyen district, Vinh Phuc province. Attending the ceremony were representatives of the Owner - Nihon Plast Vietnam Company Ltd., the Main contractor’s representatives - Hazama Ando Corporation and representatives of the Contractor - INVESTCORP.
Summer travel 2019

Summer travel 2019

On May 17-19, 2019, Investment and Development Construction Industrial Corporation INVESTCORP held its Summer travel 2019 at the tourism area Minh Chau beach, Quan Lan, Quang Ninh.
Handover of renovation project of Lam Son square – Thanh Hoa City

Handover of renovation project of Lam Son square – Thanh Hoa City

By the end of Apr 2019, the renovation project of Lam Son square – Thanh Hoa City which is constructed by INVESTCORP Land Thanh Hoa – An affiliated company of INVESTCORP was handed over to the Owner to put into use ahead the required schedule.