Update construction progress – Golden Land Project Pharmaceutical Factory in Aug 2019

Update construction progress – Golden Land Project Pharmaceutical Factory in Aug 2019

In August 2019, some items of the Kalbe pharmaceutical factory project were completed and handed over to put into use by INVESTCORP Myanmar such as internal concrete road, sedimentation system, pumping pits, parking area and drainage system.
Handover of Vietnam Mie factory project phase 2

Handover of Vietnam Mie factory project phase 2

By the end of Aug 2019, INVESTCORP has completed all items of the Vietnam Mie factory project phase 2 and handed over to the Owner to put into use.
INVESTCORP visits and works with KAM HING Group in China

INVESTCORP visits and works with KAM HING Group in China

On a business trip to China from July 31, 2019 to August 8, 2019, the Board of Directors of INVESTCORP led by Mr. Do Ngoc Dao - Chairman of the Board of Directors and General Director visited and worked with Leadership of KAM HING Group - The world's leading manufacturer of textile, dyeing, bleaching, shaping and vertically integrated finish.
INVESTCORP visits and works with INTCO Group in China

INVESTCORP visits and works with INTCO Group in China

On August 6, 2019, accepting the invitation of INTCO Group, INVESTCORP's Board of Directors visited and worked at the Group's factories in Shandong province, China. On behalf of INTCO Group, Mr. Ky Tri Sieu - Assistant to the Group’s Board of Directors, Mr. Luu Cong - Director of the Design Institute, Mr. Ly Kien Tai - Managing Director of Shandong Intco Recycling Resources Company and the staffs in charge of INTCO's foreign affairs were present to welcome the delegation.
INVESTCORP visits and works with SOUTH ASIA Group in China

INVESTCORP visits and works with SOUTH ASIA Group in China

On the morning of August 5, 2019, INVESTCORP's Board of Directors visited SOUTH ASIA Group's factory in Nan An town, Quanzhou district, Fujian province, China. Welcoming the delegation included Mr. Lu Tu Lang - Vice Chairman of the Group, Mr. Luu Tri Dan - Director of the factory and some other officials.
INVESTCORP holds periodical health check in 2019 for employees

INVESTCORP holds periodical health check in 2019 for employees

On July 24-25, 2019, Investment and Development Construction Industrial Corporation – INVESTCORP cooperated with Thien Duc international general hospital to hold a health check for all employees of the Corporation.
Update construction progress of Textile dyeing and garment factory project– Ramatex Nam Dinh in July 2019

Update construction progress of Textile dyeing and garment factory project– Ramatex Nam Dinh in July 2019

In July 2019, at the textile area, INVESTCORP completed construction of the corrugated iron walls and is now installing roof drainage pipes. Auxiliary items such as power room, transformer room and compressor room have been completed. Toilet area is under construction of tiling work. Finishing of gypsum walls, false ceiling, paint, installation of doors and windows are being urgently executed. In the first half of August 2019, INVESTCORP will complete all items and hand over the site to the Owner to carry out installation of machines.
Update construction progress of Vietnam Mie factory project phase 2 in July 2019

Update construction progress of Vietnam Mie factory project phase 2 in July 2019

At the end of July 2019, INVESTCORP completed gypsum walls and ceiling, installed steel doors, aluminum doors, painting work and Epoxy floor paint. At present, finishing details for the entire project have been completed and will be carried out internal inspection on July 31, 2019.
Update construction progress of Tamada Office and Warehouse project in July 2019

Update construction progress of Tamada Office and Warehouse project in July 2019

At the end of July 2019, INVESTCORP Myanmar completed all finishing works for the steel structure of the main factory area and started carrying out acceptance work. Painting of the ceiling and beams of the structure at the first floor has also begun.
Update construction progress – Sankyo project in July 2019

Update construction progress – Sankyo project in July 2019

In July 2019, INVESTCORP Myanmar speeded up the implementation of all items of the project. At the outdoor area, concrete road and drainage ditches have been basically completed. For the factory, INVESTCORP Myanmar has completed concrete work, plastering work and is carrying out finishing work.
Update construction progress – Golden Land Project Pharmaceutical Factory in July 2019

Update construction progress – Golden Land Project Pharmaceutical Factory in July 2019

In July 2019, although heavy rain caused difficulties for construction of the project, INVESTCORP Myanmar still tried to overcome to construct the project to meet the schedule.
Groundbreaking ceremony of Yukioh factory project

Groundbreaking ceremony of Yukioh factory project

On July 17, 2019, INVESTCORP Myanmar held the Groundbreaking ceremony of Yukioh factory project at Lot BH 2-1, Thilawa special economic zone B, Yangon, Myanmar.
Update construction progress of Textile dyeing and garment factory project– Ramatex Nam Dinh in June 2019

Update construction progress of Textile dyeing and garment factory project– Ramatex Nam Dinh in June 2019

In June 2019, INVESTCORP completed construction of the corrugated iron roof and is executing construction of the corrugated iron walls at the textile area. Currently, the ground concrete and the putty work of the internal and external walls have also been completed, the auxiliary items such as power room and toilets are being urgently carried out. In July 2019, INVESTCORP will complete the corrugated iron walls, installation of troughs, drainage pipes and other finishing works related to the corrugated iron walls. Painting work, installation of doors, false ceilings, drywall, gypsum walls and toilet tiling etc. will also be executed in July 2019.
Update construction progress of Vietnam Mie factory project phase 2 in June 2019

Update construction progress of Vietnam Mie factory project phase 2 in June 2019

By the end of June 2019, main finishing work for the whole project of Vietnam Mie factory phase 2 has been basically completed by INVESTCORP. Painting work, tiling work and gypsum partition and ceiling are now being executed final works. Erection of the aluminum and steel fire rated doors have been done. Connection work with the Factory phase 1 is also completed. Auxiliary items such as concrete road and some other items are also been done.
Update construction progress of EMS extension project of Meiko Electronics Vietnam Company Ltd in June 2019

Update construction progress of EMS extension project of Meiko Electronics Vietnam Company Ltd in June 2019

In June 2019, INVESTCORP completed and handed over the entire EMS extension project of Meiko Electronics Vietnam Company Ltd to put in use.