Update construction progress of Tamada Office and Warehouse project in Mar 2019

Update construction progress of Tamada Office and Warehouse project in Mar 2019

In Mar 2019, at the office area, INVESTCORP Myanmar completed beam and slab items of the 1st floor and assembly of roof and surrounding iron fence. Plastering work at the office is being carried out. As expected in Apr 2019, INVESTCORP Myanmar will proceed casting ground slab concrete.
Update construction progress of Myanmar Meranti project’s Ruby in Mar 2019

Update construction progress of Myanmar Meranti project’s Ruby in Mar 2019

By the end of Mar 2019, at the Myanmar Meranti project’s Ruby, INVESTCORP Myanmar is continuing implementing painting work, finish of concrete surface and finish of ancillary items. Dropped ceiling together with tank system and ancillary machine PITs are also being completed to hand over.
Update construction progress in Mar 2019 – Golden Land Project Pharmaceutical Factory

Update construction progress in Mar 2019 – Golden Land Project Pharmaceutical Factory

In Mar 2019, INVESTCORP Myanmar finished all temporary items of the Golden Land Project Pharmaceutical Factory consisting of temporary office, workshop and drainage system.
Update construction progress of Textile dyeing and garment factory project– Ramatex Nam Dinh in Feb 2019

Update construction progress of Textile dyeing and garment factory project– Ramatex Nam Dinh in Feb 2019

At the end of Feb 2019, at the Textile area of the Textile dyeing and garment factory project– Ramatex Nam Dinh, INVESTCORP finished construction of the foundation framework’s concrete, foundation pit’s backfilling and is carrying out foundation bracing. It is expected that in Mar 2019, the foundation bracing’s concrete will be finished to move to construction of the ground, walls and steel structure assembly.
Update construction progress of Vietnam Mie factory project phase 2 in Feb 2019

Update construction progress of Vietnam Mie factory project phase 2 in Feb 2019

In Feb 2019, INVESTCORP finished 50% of the foundation framework, beam and bracing at the workshop of the Vietnam Mie factory project phase 2. All construction stages are inspected by the Owner before moving to next steps.
Update construction progress of EMS extension project of Meiko Electronics Vietnam Company Ltd in Feb 2019

Update construction progress of EMS extension project of Meiko Electronics Vietnam Company Ltd in Feb 2019

In Feb 2019, INVESTCORP finished all plastering work inside the workshop, finished epoxy and iron fence at the temporary warehouse. The temporary warehouse is now handed over to the Owner to put into use.
Update construction progress of HTMP mold and plastic part manufacturing project in Feb 2019

Update construction progress of HTMP mold and plastic part manufacturing project in Feb 2019

By the end of Feb 2019, after nearly 7 months of construction at the HTMP mold and plastic part manufacturing project, INVESTCORP has completed to 95% of the indoor items. At the moment, the final finishing works are carried out.
Update construction progress of Tamada Office and Warehouse project in Feb 2019

Update construction progress of Tamada Office and Warehouse project in Feb 2019

In Feb 2019, at the office area, INVESTCORP Myanmar finished the piling work and construction of the pile caps. The foundation beam and bracing are started implementing. It is expected that the assembly of the steel structure will be carried out and completed in Mar 2019.
Update construction progress of Myanmar Meranti project’s Ruby in Feb 2019

Update construction progress of Myanmar Meranti project’s Ruby in Feb 2019

In Feb 2019, at the Myanmar Meranti project’s Ruby of Meranti Ltd., INVESTCORP Myanmar continues to implement brickwork and plastering work of some ancillary houses.
New year opening ceremony 2019

New year opening ceremony 2019

In the morning of Feb 11, 2019 – the 7th day of the Year of the Pig, Investment and Development Construction Industrial Corporation held the New year opening ceremony of the Year of the Pig 2019 at its headquarters.
Update construction progress of Vietnam Mie factory project phase 2 in Jan 2019

Update construction progress of Vietnam Mie factory project phase 2 in Jan 2019

By the end of Jan 2019, at the Vietnam Mie factory project phase 2, all the temporary works such as office, warehouse, roads and gate etc. are done by INVESTCORP. Test piles are also finished to carry out massive piling work. At present, all the massive piling work are also completed.
Update construction progress of EMS extension project of Meiko Electronics Vietnam Company Ltd in Jan 2019

Update construction progress of EMS extension project of Meiko Electronics Vietnam Company Ltd in Jan 2019

In Jan 2019, INVESTCORP has finished the entire brickwork of the surrounding wall and partitions inside the workshop from the 1st floor to the roof technical floor, completed waterproofing work and heat resistance for the roof.
Update construction progress of HTMP mold and plastic part manufacturing project in Jan 2019

Update construction progress of HTMP mold and plastic part manufacturing project in Jan 2019

By the end of Jan 2019, at the office area, INVESTCORP is proceeding finishing works such as tiling, painting, ceiling and partition, installation of doors, windows and aluminum cladding. As expected, the whole office will be finished on Feb 2, 2019.
Update construction progress of Myanmar Meranti project’s Ruby in Jan 2019

Update construction progress of Myanmar Meranti project’s Ruby in Jan 2019

By the end of Jan 2019, at the Myanmar Meranti project’s Ruby of Meranti Ltd., INVESTCORP Myanmar is continuing to implement brickwork of some auxiliary houses and finish concrete surface of the cable trough. Painting work has started being implemented.
Update construction progress of KMN Myanmar hot dip galvanizing factory project in Jan 2019

Update construction progress of KMN Myanmar hot dip galvanizing factory project in Jan 2019

In Jan 2019, INVESTCORP Myanmar has implemented the remaining works such as internal road surface at the workshop area, asphalt filling at road construction joints, completion of assembly of the company’s logo, painting of gate and fence, finish of LPG station’s removal as per new design. Grass planting and backfilling work of road curb have been completed.