News

Construction progress of Vientiane (Laos) International Airport Terminal Expansion Project in September 2017

Construction progress of Vientiane (Laos) International Airport Terminal Expansion Project in September 2017

At present, the Vientiane (Laos) international airport terminal expansion project is stepping into handover stage. At the international passenger terminal West (IPTB West), after handover of the 1st stage, all categories of the 2nd stage have been started implementing and expected to be done on 13 Oct 2017.  The outdoor area is also being carried out to handover on 30 Nov 2017.
Construction progress of Biel Crystal Vietnam Factory Project in Sep 2017

Construction progress of Biel Crystal Vietnam Factory Project in Sep 2017

In Sep 2017, the construction contractor INVESTCORP has completed 100% of concrete and plastering wok for the whole project of Biel Crystal Vietnam Factory. Painting work has also been finished to 80% and basically finished structure category.
Update construction progress in Sep 2017 at Taiyo Nippon Sanso Myanmar Project.

Update construction progress in Sep 2017 at Taiyo Nippon Sanso Myanmar Project.

In September 2017, the Construction contractor INVESTCORP continued completing and handing-over some other items of the auxiliary areas at the Taiyo Nippon Sanso Myanmar project to the Owner such as ASP building, power room and substation.
Update construction progress in Aug 2017 at Taiyo Nippon Sanso Myanmar Project.

Update construction progress in Aug 2017 at Taiyo Nippon Sanso Myanmar Project.

In August 2017, with construction efforts of the Contractor INVESTCORP to ensure progress of the project, at the Office building, INVESTCORP has completed the ground work and is carrying out the gypsum ceiling-partition and painting work. All of the key items will be completed in September 2017.
Construction progress of Vientiane (Laos) international airport terminal expansion project in August 2017

Construction progress of Vientiane (Laos) international airport terminal expansion project in August 2017

In August 2017, construction of the Vientiane (Laos) international airport terminal expansion project has been urgently implemented to ensure the overall progress of the project.
Construction progress of Biel Crystal Vietnam Factory Project in August 2017

Construction progress of Biel Crystal Vietnam Factory Project in August 2017

For each project, besides important factors of safety and quality, progress is also a very important one. Therefore, the construction Contractor- INVESTCORP always tries its best not only to ensure the three above-mentioned factors but also to complete the project beyond planned progress and the Biel Crystal Vietnam Factory project is an example. As expected, the whole Factory will be handed-over to the Owner and put into use in this September 2017.
Groundbreaking ceremony of Wearing apparel manufacturing Project – Ramatex Hai Phong.

Groundbreaking ceremony of Wearing apparel manufacturing Project – Ramatex Hai Phong.

In the morning of August 17 2017, Ramatex Group and Investment & Development Construction Industrial Corporation – INVESTCORP formally held the Groundbreaking ceremony of Wearing apparel manufacturing project at VSIP Hai Phong Industrial Park in Tan Duong commune, Thuy Nguyen district, Hai Phong city. The ceremony was attended by the Owner – Ramatex Group and its partners together with the whole Management Board and staffs of the Construction contractor – INVESTCORP.
Construction progress updated in July 2017 at Vientiane (Laos) international airport terminal expansion project.

Construction progress updated in July 2017 at Vientiane (Laos) international airport terminal expansion project.

At present, finishing work for both internal and external areas of the International passenger terminal West (IPTB West) is urgently executed for timely handing-over to the Owner on August 25, 2017.  It is expected that by Aug 20, 2017, after finishing plastering and tiling external wall, the scaffolding system for outer construction will be dismantled. Concrete for drainage system is still being carried out and will be finished on Aug 15, 2017. The internal construction items such as tiling, gypsum wall and ceiling, wood doors and aluminum doors are also executed in line. All of the Vinyl floor, carpet and painting work consisting of both emulsified paint and rough paint have been completed.
Construction progress updated in July 2017 at Taiyo Nippon Sanso Myanmar project.

Construction progress updated in July 2017 at Taiyo Nippon Sanso Myanmar project.

By the end of July 2017, after executing the construction with the best efforts of the construction contractor –INVESCORP for nearly 05 months to catch up the tight schedule of the project, some main items have been finished. At present, all beam and slab formworks of the 1st floor and roof floor at the office building have been dismantled. Brickwork and plastering at the 1st floor have also been being executed and expected to finish in August 2017. Gypsum wall and ceiling are carried out in line.
Construction progress updated in July 2017– Biel Crystal Vietnam Factory Project.

Construction progress updated in July 2017– Biel Crystal Vietnam Factory Project.

More than two months after the groundbreaking ceremony on May 23, 2017, construction of the Biel Crystal Vietnam Factory project has been gradually come into stability. All of the temporary works for construction of the project such as fence, office, workers’ house, entrance gate and site signals have been finished.
Update constructing progress in June 2017 – Vientiane (Laos) international airport terminal expansion construction project

Update constructing progress in June 2017 – Vientiane (Laos) international airport terminal expansion construction project

As of the end of June 2017, at the Western passenger terminal, all of the interior and exterior completion works have been synchronously implemented in order to ensure partial handover to the Owner to put into use at the end of August 2017. In addition, other works have been done at the same time.
Update construction progress in June 2017 – Taiyo Nippon Sanso Myanmar Project.

Update construction progress in June 2017 – Taiyo Nippon Sanso Myanmar Project.

After many months of bad weather, until June 2017, managers and engineers at the Taiyo Nippon Sanso Gas Factory construction site have continued to uphold the construction to ensure good quality and timely schedule as required by the Investor and the Contractor.
Summer Travel 2017

Summer Travel 2017

Thanks to the care and facilitation of the Board of Directors of the Company, from June 9-11, 2017, the union of Investment and Development Construction Industrial Corporation held a tour for summer 2017 in Co To island district – Quang Ninh province.
Update construction progress in May 2017 – Vientiane (Laos) international airport terminal expansion project

Update construction progress in May 2017 – Vientiane (Laos) international airport terminal expansion project

Up to the end of May 2017, at the IPTB West, finishing work such as ceiling, gypsum board, paint work, plastering and tiling, etc. has been continuously progressed. External work such as concrete ditches and utility facilities has been developed as well.
Update construction progress in May 2017 – Taiyo Nippon Sanso Myanmar Project.

Update construction progress in May 2017 – Taiyo Nippon Sanso Myanmar Project.

In May 2017, it was rainy in Yangon, the works at the Taiyo Nippon Sanso project have been encountered many difficulties. However, with the determined spirit, the team of engineers and workers on the construction site has worked hard to ensure the expected schedule.