Update construction progress – Lakeside Service Apartment (Myanmar) project in September 2020

Update construction progress – Lakeside Service Apartment (Myanmar) project in September 2020

In September 2020, INVESTCORP Myanmar completed the piling work and is now focusing on excavation in combination with the installation of the remaining piling support system. The construction of reinforced concrete structures in the basement started to be executed including lean concrete pouring, reinforcing fabrication and installation of formwork of foundation framework.
Update construction progress – Technical Infrastructure Project of Dong Nam New Residential Area, Dong Khe Commune, Dong Son District, Thanh Hoa Province in September 2020

Update construction progress – Technical Infrastructure Project of Dong Nam New Residential Area, Dong Khe Commune, Dong Son District, Thanh Hoa Province in September 2020

Dong Nam residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province, invested by the Management Board of construction and investment projects of Dong Son district having an area of nearly 10ha. Dong Nam residential area infrastructure project was commenced on July 3, 2020 by INVESTCORP Land Thanh Hoa Company Limited including traffic roads, water supply and drainage system, power supply system, green infrastructure and balancing reservoir.
Update construction progress – Crystal Martin Vietnam factory project in September 2020

Update construction progress – Crystal Martin Vietnam factory project in September 2020

In September 2020, INVESTCORP continued to execute the renovation of the 6th floor of R1C building into an office at the Crystal Martin Vietnam factory project.
2nd anniversary of establishment of INVESTCORP Land Thanh Hoa Company Limited

2nd anniversary of establishment of INVESTCORP Land Thanh Hoa Company Limited

On September 19, 2020, the 2nd anniversary of INVESTCORP Land Thanh Hoa Company Limited was held at the Company's headquarters No. 166 Trieu Quoc Dat, Dien Bien Ward, Thanh Hoa City. Attending the ceremony was the presence of the Board of Directors and all staff of the Company.
Groundbreaking ceremony of Suga International (Vietnam) Factory Projects

Groundbreaking ceremony of Suga International (Vietnam) Factory Projects

On the morning of September 18, 2020, the Groundbreaking ceremony of Suga International (Vietnam) Factory Project was held at lot CN11-3, Que Vo 3 Industrial Park, Que Tan commune, Que Vo district, Bac Ninh province. The ceremony was fully attended by representatives of Investor - Suga International (Vietnam) Company Limited, representatives of Management Board of Que Vo 3 Industrial Park and representatives of Construction Contractor - INVESTCORP Company.
Update construction progress – Phase 4 factory construction project of Yokowo Vietnam Co., Ltd in August 2020

Update construction progress – Phase 4 factory construction project of Yokowo Vietnam Co., Ltd in August 2020

At the end of Aug 2020, INVESTCORP has completed all concrete foundation for the expanded area of the Main factory - Phase 4 factory construction project of Yokowo Vietnam Co., Ltd and started the construction of gypsum ceiling. It is expected that in September 2020, INVESTCORP will complete 50% of the paint workload and implement windows and fire-rated windows.
Update construction progress of Textile dyeing and garment factory project – Ramatex Nam Dinh phase 2 in August 2020

Update construction progress of Textile dyeing and garment factory project – Ramatex Nam Dinh phase 2 in August 2020

In August 2020, INVESTCORP completed all the concrete structures in Zone 1, Zone 2 and the wall construction in Zone 1 of the Main factory of the Textile dyeing and garment factory project – Ramatex Nam Dinh phase 2. It is expected that in September 2020, INVESTCORP will complete structural concrete in Zone 3 and build walls of the 2nd, 3rd and 4th floors in Zone 2.
Update construction progress – Lakeside Service Apartment (Myanmar) project in August 2020

Update construction progress – Lakeside Service Apartment (Myanmar) project in August 2020

At the end of August 2020, the Lakeside Service Apartment (Myanmar) project continued to be piled by INVESTCORP Myanmar and started excavation work, installed shoring system and cut bored pile heads. Currently, INVESTCORP Myanmar has completed 85% of the piling works and it is expected to be completed on September 10, 2020.
Update construction progress – Crystal Martin Vietnam factory project in August 2020

Update construction progress – Crystal Martin Vietnam factory project in August 2020

Crystal Martin Vietnam factory project is located in Quang Chau Industrial Park - Viet Yen - Bac Giang, consisting of the two items of domestic wastewater treatment station and renovation of the 6th floor of R1C building into an office.
Handover of Meiko Quang Minh electronics assembling factory project

Handover of Meiko Quang Minh electronics assembling factory project

At the end of August 2020, all items of Meiko Quang Minh electronics assembling factory project were completed by INVESTCORP. Currently, the project is being inspected and handed over to the Investor - Meiko Electronics Vietnam Co., Ltd.
Update construction progress – Phase 4 factory construction project of Yokowo Vietnam Co., Ltd in July 2020

Update construction progress – Phase 4 factory construction project of Yokowo Vietnam Co., Ltd in July 2020

In July 2020, at the Phase 4 factory construction project of Yokowo Vietnam Co., Ltd, construction items continued to be carried out by INVESTCORP to catch up with the progress submitted to the Investor.
Updated construction progress - Electrical decoration project of Cau Ke street in July 2020

Updated construction progress - Electrical decoration project of Cau Ke street in July 2020

At the end of June 2020, INVESTCORP Land Thanh Hoa completed installation of the remaining two double light poles and connected electricity for the whole line to run commission on June 28, 2020. On July 10, 2020, the project was officially put into operation.
Update construction progress in July 2020 – Embellishment project of Rung Thong historic sites and landscapes

Update construction progress in July 2020 – Embellishment project of Rung Thong historic sites and landscapes

In July 2020, INVESTCORP Land Thanh Hoa mobilized necessary resources to complete the project and handed it over to the Investor to hold the project inauguration ceremony before the XXV Party Congress of Dong Son district for the term 2020-2025.
Update construction progress – Lakeside Service Apartment (Myanmar) project in July 2020

Update construction progress – Lakeside Service Apartment (Myanmar) project in July 2020

INVESTCORP Myanmar is now executing piling work for the basement construction of the Lakeside service apartment (Myanmar) project.
Update construction progress – Meiko Quang Minh electronics assembling factory project in July 2020

Update construction progress – Meiko Quang Minh electronics assembling factory project in July 2020

In July 2020, INVESTCORP continued its efforts to carry out the Meiko Quang Minh electronics assembling factory project to hand over to the Investor on time.