Update construction progress of Textile dyeing and garment factory project – Ramatex Nam Dinh phase 2 in July 2020

Update construction progress of Textile dyeing and garment factory project – Ramatex Nam Dinh phase 2 in July 2020

At the end of July 2020, INVESTCORP has completed 50% of the Main factory's structure and has completed the construction of walls at floors 1, 2, and 3 in Zone 1. It is expected that in August 2020, INVESTCORP will finish casting  all structural concrete in Zone 2; continue construction of columns, beams, floors 2 and 3 in Zone 3; build brick walls of the 4th floor in Zone 1 and the walls at the 1st floor, 2nd floor of Zone 2.
Signing ceremony of cooperation agreement for developing Xuan Tien INVESTCORP residential area project

Signing ceremony of cooperation agreement for developing Xuan Tien INVESTCORP residential area project

On June 26, 2020 at Vinpearl Hotel - Thanh Hoa City, the signing ceremony of cooperation agreement for developing Xuan Tien INVESTCORP residential area project took place between the Project Investor - Investment and Development Construction Industrial Corporation - INVESTCORP and the Joint Venture of Hai Khang Investment and Development Joint Stock Company - M-land Thanh Hoa Joint Stock Company.
Handover of Yukioh factory project

Handover of Yukioh factory project

On June 20, 2020, the Yukioh Factory project was handed over to the Investor - Yukioh Japan Co., Ltd by INVESTCORP Myanmar.
Update construction progress in June 2020 – Embellishment project of Rung Thong historic sites and landscapes

Update construction progress in June 2020 – Embellishment project of Rung Thong historic sites and landscapes

On June 17, 2020, INVESTCORP Land Thanh Hoa Co., Ltd carried out the renovation of Rung Thong historic sites and landscapes in Rung Thong town, Dong Son district, Thanh Hoa province with the total construction investment capital of more than 12.9 billion VND.
Updated construction progress - Electrical decoration project of Cau Ke street in June 2020

Updated construction progress - Electrical decoration project of Cau Ke street in June 2020

Carrying out the electricity package for decorating Cau Ke street, belonging to the embellishment project of towns and urban centers in Tho Xuan district, in June 2020 as per the Investor’s request, INVESTCORP Land Thanh Hoa Co., Ltd completed the installation of 15 out of 17 double light poles (at both sides of the road) and 31 single light poles (in the middle of the road). It is estimated to reach over 95% of the contract volume.
Update construction progress of Textile dyeing and garment factory project – Ramatex Nam Dinh phase 2 in June 2020

Update construction progress of Textile dyeing and garment factory project – Ramatex Nam Dinh phase 2 in June 2020

In June 2020, INVESTCORP has completed all ground works and columns of the first floor in the Main factory, completed casting concrete of the fourth floor in Zone 1. As expectation in July 2020, INVESTCORP will complete the entire structural work in Zone 1 and continue to carry out columns, beams and floors of the second floor and third floor in Zone 2.
Handover of Traditional building project of Tho Xuan district

Handover of Traditional building project of Tho Xuan district

In June 2020, INVESTCORP Land Thanh Hoa has completed and handed over the Traditional building project of Tho Xuan district ahead of schedule to the Investor to put into use on the occasion of welcoming the Tho Xuan District Party Congress, term 2020-2025.
Update construction progress – Meiko Quang Minh electronics assembling factory project in June 2020

Update construction progress – Meiko Quang Minh electronics assembling factory project in June 2020

In June 2020, INVESTCORP has completed the construction of the attic columns, attic beams and slabs of the Main factory. Currently, INVESTCORP is continuing to install the wall purlins, corrugated walls, roof waterproofing and some other finishing items such as plastering and staircase finishing etc.
Update construction progress - Yukioh factory project in May 2020

Update construction progress - Yukioh factory project in May 2020

In May 2020, INVESTCORP Myanmar continued its efforts to implement at the same time the remaining work items of the Yukioh project to ensure the acceptance and handover schedule to the Investor.
Update construction progress – Traditional building project of Tho Xuan district in May 2020

Update construction progress – Traditional building project of Tho Xuan district in May 2020

By the end of May 2020, INVESTCORP Land Thanh Hoa has completed 95% of the construction under the contract with the Investor and is speeding up construction of the floor tiles on the second and third floors, completion of the painting work, erection and finishing of glass walls and automatic door systems...
Update construction progress – Meiko Quang Minh electronics assembling factory project in May 2020

Update construction progress – Meiko Quang Minh electronics assembling factory project in May 2020

By the end of May 2020, the items of the Main factory area have been completed by INVESTCORP including construction of the columns, slabs and beams, staircases of the second floor, third floor and roof floor. Construction of the columns, beams and attic floor reached 50% of the workload, brickwork and plastering work and staircases of the first floor reached 80%.
Update construction progress of Textile dyeing and garment factory project – Ramatex Nam Dinh phase 2 in May 2020

Update construction progress of Textile dyeing and garment factory project – Ramatex Nam Dinh phase 2 in May 2020

By the end of May 2020, in the Main factory area, INVESTCORP has fully completed the construction of 15,000m2 of the ground and 60% of the 1st floor columns. The column structures, slabs and beams of the second, third and fourth floors and the roof floor are divided into 3 zones (from Zone 1 to Zone 3) and will be constructed respectively. At the moment, the concrete work of the second floor has been completed 20% of the workload and it is expected that in June 2020, INVESTCORP will carry out concrete casting of the first floor columns, column concrete, beams and slabs of the second, third and fourth floors and continue constructing the roof floor of Zone 1.
Groundbreaking ceremony of Phase 4 factory construction project of Yokowo Vietnam Co., Ltd

Groundbreaking ceremony of Phase 4 factory construction project of Yokowo Vietnam Co., Ltd

On the morning of May 28, 2020, INVESTCORP held the groundbreaking ceremony of the Phase 4 factory construction project invested by Yokowo Vietnam Co., Ltd and the Main contractor - Hazama Ando Corporation. The project is constructed in Dong Van II Industrial Zone - Duy Tien district - Ha Nam province.
Seminar on reorganizing work procedures, guiding implementation of safety procedures and periodical reports

Seminar on reorganizing work procedures, guiding implementation of safety procedures and periodical reports

Meeting the needs of expansion and development towards the 10th anniversary of the Corporation's establishment, on May 13&14, 2020, Investment and Development Construction Industrial Corporation organized a Seminar to reorganize the work procedures between the Corporation’s departments and the Member companies, Divisions and Construction teams under INVESTCORP; guide the implementation and application of safety procedures, and guide the implementation of periodical reports.
Update construction progress – Meiko Quang Minh electronics assembling factory project in April 2020

Update construction progress – Meiko Quang Minh electronics assembling factory project in April 2020

In April 2020, INVESTCORP completed the construction of the factory ground area including sand leveling, base spreading and compaction, moisture-proof nylon lining, installation of formwork and welded wire mesh, casting concrete and finishing concrete surface.